Warehouse relocation without stopping deliveries. How to plan the transfer of inventory and operations?

Warehouse relocation without stopping deliveries. How to plan the transfer of inventory and operations?

 

In the first quarter of 2026, new lease agreements and expansions accounted for 54% of the demand for warehouse space in Poland. However, changing facilities means the necessity of simultaneously transferring inventory, launching systems, and fulfilling current orders. How to carry out a relocation so that customers do not wait for deliveries due to organizational problems? The most important factors are the correct sequence of actions and confirming the readiness of the new hall before moving key products.

 

When to start planning a warehouse relocation?

The return date for the current hall must be reduced by the time required for final inventory, dismantling equipment, repairs, and the facility handover to the owner. The last day of the contract should not be the date of the last shipments from the old location.

Preparations can take from several to over a dozen months. The scope of work depends on the facility’s area, the number of SKUs, storage methods, fire safety requirements, and the degree of automation. Additional time is required for rack assembly, increasing power connection capacity, preparing the IT network, and adapting production or cold storage areas.

Already at the stage of selecting a new hall, the company should know:

  • the minimum number of pallet spaces;
  • the required area for receiving, picking, and shipping zones;
  • the number of docks and ground-level gates;
  • energy demand;
  • fire protection requirements;
  • the deadline by which the facility must be ready for testing.

Available spaces can be initially compared at https://wynajemmagazynu.pl/. The final list of facilities should take into account the handover date and the time needed for adaptation, as the mere availability of space does not mean readiness to start operations.

How to prepare a warehouse relocation schedule?

The schedule should combine technical work, inventory transport, system launch, employee training, and handling current orders. Each stage requires a completion deadline and a criterion confirming that the next one can begin.

An example plan for a distribution warehouse might look like this:

Deadline before launch Scope of activities
6–9 months location selection, contract negotiations, warehouse layout design, defining technical requirements
3–6 months hall adaptation, ordering racks and equipment, preparing IT network, selecting a transport company
6–8 weeks inventory count, assigning new locations, preparing transport sequence
2–4 weeks WMS, scanner, and printer tests, trial receipts, moving slow-moving products
switchover week transport of operational inventory, stock control, launching full picking
1–2 weeks after launch adjusting product placement, emptying the old warehouse, preparing the hall for return

Deadlines should be adjusted to the scope of the project. Relocating a cold store, production warehouse, or a facility with automation may require additional inspections and longer tests.

The contingency plan should specify where orders will be fulfilled if the new location does not reach the assumed efficiency. The company can temporarily leave part of the inventory in the old hall, use an external operator, or postpone deliveries whose timing does not affect production and sales continuity.

Are two warehouses needed during relocation?

Several days or weeks of parallel use of both facilities increase expenses for rent, security, utilities, and personnel. However, such a period allows for the gradual launch of processes without moving the entire inventory at once.

Overlapping contracts are particularly important when the company:

  • fulfills a large number of orders every day;
  • supplies production in a continuous system;
  • handles products with short delivery times;
  • is moving automation or complex installations;
  • cannot temporarily replace the warehouse with an external service.

The new hall should undergo a trial covering the full order path: receiving goods, recording them in the system, putting them away on the rack, picking, packing, printing documents, and handing the shipment to the carrier. Only the result of such a test allows assessing whether the facility can take over fast-moving products.

The decision to close the old warehouse should be dependent on achieving target parameters in the new location. This includes, among other things, inventory accuracy, shipping timeliness, and the assumed efficiency of receipts and picking. If the team maintains these results for several consecutive days without using contingency procedures, it is safe to finish work at the previous location. The cost of an additional week of parallel rent is often much lower than the consequences of lost inventory, delayed orders, and a pile-up of complaints — explains Łukasz Marynowski, an expert in commercial real estate from wynajemmagazynu.pl

In what order should goods be moved to the new warehouse?

Priority should be given to products whose temporary unavailability will not stop current sales or production. The sequence of transports can be determined based on ABC analysis, pick history, and pending orders.

Group C goods, ordered sporadically, can usually be moved earlier. Group A products should remain in the operational warehouse until the efficiency of the new location is confirmed. Part of the stock of fast-moving SKUs can be divided between both facilities to limit the effects of transport delays or system failures.

Before relocation, it is also necessary to separate:

  • inventory intended for sale;
  • damaged or returned goods;
  • products being withdrawn from the offer;
  • units without a confirmed location;
  • stocks requiring special transport conditions.

Transporting inactive stock generates transport costs, takes up space in the new facility, and hinders inventory.

Each transport unit should have a pre-assigned destination location. Pallets brought in without labels go to the buffer zone, where they wait for re-identification and a decision by the warehouse worker. With a large number of transports, such organization quickly blocks the receiving zone.

Relocation also allows for changing the storage layout. Products with the highest number of picks can be placed closer to the picking area, and heavy or bulky goods in zones that limit the number of additional trips. Copying the layout of the old warehouse makes sense only if the current arrangement corresponds to the current order structure.

How to maintain shipments and receipts during a warehouse move?

For the switchover week, it is worth limiting the number of operations that can be performed earlier or postponed without affecting customers. The company can increase the stock of high-rotation products, accelerate selected deliveries, and change the dates of receipts for materials that are not needed for current production.

Suppliers should receive the exact date of the address change and information on which facility to direct specific groups of products to. A simple announcement about the opening of a new warehouse is not enough if both receiving locations are operating for several days.

Carriers picking up shipments must know:

  • the date of the first pickup;
  • working hours;
  • notification method;
  • entry rules;
  • gate location;
  • the person responsible for receiving the driver.

Returns require a separate plan. Customers and couriers may continue to direct shipments to the previous address for some time. The company should determine who will pick them up, how they will be transported, and in which system they will be re-received.

To which location should the warehouse be moved?

The new location should correspond to the supply structure, employee availability, and the company’s development plans. A larger hall located further from customers may lower rent while simultaneously increasing transport costs and extending order fulfillment times.

In the first quarter of 2026, the highest tenant activity was recorded in the Masovian, Greater Poland, Lower Silesian, and Łódź voivodeships. These regions have extensive space resources and access to main routes, which is why companies have a greater choice of modules with various parameters there.

Central Poland is considered by companies handling domestic distribution due to the connection of the A1 and A2 motorways. In 2025, the demand for warehouse space in the Łódź voivodeship reached 1.17 million m², and total resources exceeded 5.1 million m².

Companies considering this region can check available properties at https://wynajemmagazynu.pl/przestrzenie-magazynowe/lodz/. When comparing offers, one must add the number of kilometers on routes to customers and suppliers, employee commute time, and the possibility of expanding the module in subsequent years.

How to check the readiness of the new warehouse before relocation?

Before the first transport, elements resulting from the tenant’s specifications should be accepted and then checked during a trial operation.

Technical inspection should cover:

  • condition and load-bearing capacity of the floor;
  • operation of docks and gates;
  • sprinkler system and fire alarm system;
  • lighting and heating;
  • power connection capacity;
  • utility meters;
  • IT network;
  • road and zone marking;
  • rack protection;
  • access to social rooms.

Employees should perform a trial receipt and shipment using equipment that will be in operation after the relocation. The test allows detecting dead zones in the wireless network, incorrect location markings, a too-small put-away zone, or deficiencies in packing station equipment.

It is also necessary to prepare a work procedure in case of a WMS failure. It should specify how to manually register deliveries, where to put unrecognized units, and the rules for later entering data into the system.