The largest railway tunnel boring machine is heading to Łódź

Photo: PKP Polskie Linie Kolejowe SA

A TBM shield 115 m long, over 13 m in diameter, and weighing 1,560 tons will bore a railway tunnel in Łódź. It will create new opportunities for rail travel through Łódź and more efficient travel across the country and Europe.

PKP Polskie Linie Kolejowe SA has already accepted the work related to the TBM machine, which will be tasked with boring one of the cross-city tunnels in Łódź. The machine is manufactured by Herrenknecht in Schwanau, Germany.

– Currently, PKP Polskie Linie Kolejowe SA has secured specialized equipment, two TBM shields for the implementation of the project related to the construction of tunnels in Łódź, i.e., clearing the Łódź Railway Junction and creating new travel opportunities in Poland – said Arnold Bresch, member of the management board of PKP Polskie Linie Kolejowe SA.

The shield will bore a double-track tunnel from the launch shaft between Odolanowska and Stolarska streets, through the site of the underground stops Łódź Polesie and Łódź Śródmieście, to the Łódź Fabryczna station. The tunnel will be 3 km long and 12.7 m in diameter. It will be executed by the largest TBM machine that has worked in Poland so far. Previously, the largest diameter (12.6 m) was held by the shield that bored the road tunnel under the Martwa Wisła river in Gdańsk.

Transport by ship
The next stage, after the machine’s acceptance, is its disassembly and the transport of individual components to Łódź. The first parts may reach Poland in March. The biggest challenge will be the transport of the non-dismantlable bearing and the housing in which it is embedded, as well as four adjacent motors. Due to the large size of the shield, some of its components will be transported to Poland by ship – first along the Rhine River, then across the Baltic Sea. Subsequently, the cargo will travel to Łódź by trucks. A specialized company will be responsible for the transport. The process requires checking and preparing the roads. By April, all components should be on site.
The TBM can bore about 10 m of tunnel per day. The shield, located at the front of the machine, rotates 3 times per minute, crushing the ground. The material is continuously extracted to the surface. The bored space is then lined. The launch shaft for the large TBM shield is being built in Łódź between Odolanowska and Stolarska streets. According to the contractor’s announcements, the construction of the shaft is to be completed in June. Then, tunnel boring will begin.

Smaller shield already in Łódź
The components of the first shield are already in Łódź. It will bore 4 single-track tunnels with a diameter of 8.5 m and a total length of about 4.5 km from the turnout chamber at al. Włókniarzy to railway line no. 15 towards Łódź Żabieniec and Łódź Kaliska. The smaller “mechanical mole” weighs about 650 tons, has a diameter of 8.76 m, and is 95 m long. Its parts were transported exclusively by land using trucks.
The contractor will continuously monitor the impact of the investment on nearby buildings. Among other things, the technical condition of facilities located nearby will be checked. Vibration measurements will also be carried out.
The construction of the cross-city tunnel is a continuation of the work started with the construction of the Łódź Fabryczna station. The investment will ensure a faster connection through the city center and will also contribute to creating an effective system of national interregional connections covering the central region of Poland. Thanks to the construction of the tunnel, the Łódź Fabryczna station will change from a terminal station into a through station. Travel time will be shortened, and both regional and long-distance trains will be able to pass through the very center of Łódź – on the east-west axis (via Łódź Widzew, Fabryczna, and Kaliska stations) and on the north-south axis (via Łódź Widzew, Fabryczna, and Żabieniec stations).

Easier communication
In the tunnel, trains will be able to travel at a maximum speed of up to 100 km/h. As part of the project, two stops will also be built – Łódź Polesie and Łódź Śródmieście, which will be integrated with public transport and will facilitate daily commuting to work and school for the residents of the agglomeration.

The project titled “Clearing the Łódź Railway Junction (TEN-T), Stage II, Section Łódź Fabryczna – Łódź Kaliska/Łódź Żabieniec” is co-financed under the Infrastructure and Environment Operational Program. The value of the project is PLN 1,764,333,383.70, of which the EU subsidy is PLN 1,434,417,385.13. The design and construction of the tunnel are carried out by a consortium: Energopol Szczecin and Przedsiębiorstwo Budowy Dróg i Mostów from Mińsk Mazowiecki. The completion of the investment is planned for the end of 2022.

Source: PKP Polskie Linie Kolejowe SA