The parking lot on Śnieżna Street is the first element of a system of buffer parking lots for customers of the Port of Gdansk. The number of parking spaces at the Port of Gdansk will be gradually increased.

Cargo handling at the Port of Gdansk is growing dynamically. This leads to an increase in road traffic and a greater demand for parking spaces. In response to these challenges, the Port of Gdansk Authority has built a buffer parking lot, which has just been put into operation.
The fenced, illuminated, and monitored parking area can accommodate 62 trucks. The entrances are equipped with barriers controlled by security staff. Until the Port Authority implements a unified truck notification system, the use of the buffer parking lot is free of charge and is based on electronic notification.
The parking lot has social facilities. There is a waiting room for drivers on the premises, as well as showers and toilets. The sanitary facilities have been adapted for people with disabilities.

– The buffer parking lot was created to streamline traffic related to cargo transport. The Gdynia-based company MTM was responsible for the comprehensive implementation of the investment. The built parking lot will allow for better control of vehicle traffic. It will also contribute to saving our customers’ time. Thanks to it, drivers will be able to calmly wait for loading or unloading at the Port. The benefits of the parking lot will be felt not only by drivers and port terminal employees but also by the residents of Nowy Port, as it will eliminate congestion on Marynarki Polskiej Street – explains Marcin Osowski, Vice President of the Port of Gdansk Authority for Infrastructure.

The cost of the investment amounted to PLN 5.5 million. The construction was entirely financed from the Port of Gdansk Authority’s own funds. The buffer parking lot is the first facility at the Port of Gdansk intended exclusively for trucks serving the Port. The Port Authority plans to build three more. The first facility will be built in 2020 on Nowa Portowa Street, the second on Kontenerowa Street, and the last on Ku Ujściu Street. In total, this will provide over 500 parking spaces.

– We were very concerned about the implementation time, which is why we decided on the “design and build” formula, which accelerated the commissioning of the parking lot. We used innovative roller-compacted concrete technology, which is much more durable and cheaper than standard concrete pavement. If it proves successful, we will use it in the construction of subsequent parking lots, roads, or storage yards – says Sylwia Artichowicz, Director of the Infrastructure Maintenance Department at the Port of Gdansk Authority.