A container with frozen goods arriving at a Polish port may be subject to inspection by as many as four different authorities. Each has its own notification system, its own document workflow, and its own calendar, with scheduling handled separately via phone or email. In Hamburg and Rotterdam, these same activities are coordinated within a single system.
Clearance at the port of Hamburg begins ten days before the ship arrives, whereas in Poland, it only starts after unloading.
– says Maciej Kisiel, Board Member of the Polish Association of Fish Processors.
The Polish Association of Fish Processors points out that the difference does not stem from EU law, but from the organization of its implementation. The framework for official controls is uniform across the entire EU, as defined by Regulation 2017/625. However, this same regulation leaves member states the freedom to organize the work of their own authorities. It is precisely at this level that the difference between Gdynia, Gdańsk, Szczecin, and, for example, Hamburg arises.
Where the delay actually occurs
In Hamburg, the freight forwarder begins preparing for clearance about ten days before the ship calls at the port. They provide the container number, bill of lading number, and the method of onward transport to the import platform, and in return, they receive data from the carrier’s summary declaration. The customs declaration is filed before the goods arrive.
When the terminal reports unloading, the platform automatically transmits the status, and the declaration is confirmed without human intervention. Information on the status of veterinary documents and the scheduling of the inspection appointment also appears on the same platform.
– says Maciej Kisiel, Board Member of the Polish Association of Fish Processors.
In Western ports, such as Rotterdam, the inspection portal gives all parties a full view of scanner and physical inspections, from notification to release. In Poland, the same process starts with a PDF file in an email inbox. The customs agency enters data manually: for the temporary storage declaration, for the customs declaration, for the veterinary document in the EU system, and for terminal notification. The container number, weight, commodity code, and sender are re-typed multiple times. The inspection time for each authority is agreed upon separately.
Consequences of the lack of coordination between inspection authorities
Inspections conducted one after another instead of in parallel extend the container’s dwell time, and every day of dwell time means an additional cost for the importer. A container unloaded on Saturday waits in a Polish port until Monday because confirming the declaration requires human intervention. Inspection procedures in Polish ports take from several days to several weeks, while in Western European ports, they take from two to five days.
This translates into importer decisions: about a quarter of the industry’s shipments currently reach Poland via Western ports. According to the Association’s calculations, the Polish budget loses over 100 million PLN annually because of this. To change this, it is enough to invest about 3 million annually. The profit is surely obvious?
We are not advocating for fewer inspections. Each of them has its justification, and no one in the industry questions that. We are advocating for the container to be presented once, not several times, and for the authorities to coordinate schedules among themselves, rather than through a customs agent – says Maciej Kisiel. – We also see that the inspection authorities are currently working with staffing levels that have not kept pace with the growth of volumes in ports. Without strengthening the staff, no procedural improvement will work fully.
– adds the Board Member of the Polish Association of Fish Processors. The inspection services need an injection of cash and additional hands to work.
Industry demands
In recommendations submitted to the Working Group on Border Crossings at the Ministry of Infrastructure, the Association points to four directions:
- joint notification and a single presentation of the container for all authorities;
- a shared electronic inspection calendar;
- providing access to data from the carrier’s declaration to the authorized customs representative, along with automatic confirmation of declarations filed before the arrival of goods;
- a common IT platform that will connect existing systems instead of creating another one.
The issue is of direct importance to the Integrated Border Control Point being built at the Port of Gdańsk, where all inspection authorities will be headquartered. The completion of the first stage of the investment is planned for 2030.
Physically placing the authorities at one address will only be effective if a single coordinated inspection and a shared data workflow are implemented in parallel. Therefore, we advocate that the procedures for a single inspection be implemented and tested before the facility is handed over, so that it operates in the target model from the very first day.
– explains Maciej Kisiel.
Dialogue with the administration is ongoing: the Ministry of Infrastructure has established a Working Group on Border Crossings, in which representatives of the industry, ports, customs agencies, and inspection authorities participate. The causes of the problem have been described together – however, the decisions that would translate into shorter clearance times are still missing.
Source: Polish Association of Fish Processors