Up to 8 million pieces of clothing and accessories per week – this is the capacity of the recently launched LPP Distribution Center in Brześć Kujawski, which is heading towards full operational capacity after 3 months. The new facility, with a storage capacity of up to 40 million items, has been equipped with automation solutions enabling the simultaneous service of up to 1,000 retail stores. The center has already employed over 700 people, for whom the company has provided a modern and friendly workplace as well as comfortable commuting conditions. The facility was designed taking into account sustainable construction standards, which have been submitted for BREEAM certification.
The strategic LPP investment in Brześć Kujawski is a facility that began operations in February of this year and works in a three-shift system based on a 700-person crew.
– We started the investment in January of last year, and after less than 1.5 years, we can talk about approaching full operational efficiency of the facility by leaps and bounds. Thanks to the implemented warehouse automation solutions, the center ensures a high standard of service for our stores and, alongside the Distribution Center in Pruszcz Gdański, constitutes a key pillar of the LPP logistics network – explains Sebastian Sołtys, Logistics Director at LPP.
The center is equipped with two sorters with a unique chute design, enabling the service of up to 1,000 stores simultaneously.
– In our new distribution center, we opted for an innovative solution in the field of sorter technology. The engineering experience of the Dutch manufacturer of this type of equipment, supported by several weeks of testing, allowed us to develop a sorter design tailored to LPP’s needs. The newly patented pneumatic solution allows us today to maintain very high sorting process efficiency in continuous mode, while simultaneously increasing the efficiency of warehouse space utilization. It is worth emphasizing that the innovative pneumatic patent is also very quiet, which increases work comfort when operating such equipment – informs Michał Moteka, Process and Automation Development Manager at LPP.
Automation of operations also significantly streamlines the order picking process for stores. Thanks to this, in the first two months of operation, the warehouse in Brześć Kujawski distributed over 300,000 cartons with LPP brand collections.
The new warehouse also uses an automated labeling process, as well as machines for forming and closing cartons, which increase production efficiency and guarantee intuitive and safe operation.
The 1.8 km conveyor system installed in the center is equipped with solutions allowing for the recovery of packaging and its reuse. Support for operations is provided by a fleet of over 70 forklifts, for which a modern battery room with a battery queuing system has been prepared.
The entire facility operates with the support of a WMS (Warehouse Management System) managing the processes of goods flow, human labor, and logistics equipment.
– Thanks to these solutions, the 75,000 m2 warehouse can ensure the distribution of up to 8 million pieces of clothing and accessories per week. Additionally, a racking system with a storage capacity of 40 million pieces of clothing, i.e., up to 67,000 pallets of goods, has been installed in the facility. Such a number of pallets placed linearly would reach a total length of approx. 60 kilometers, which corresponds to the distance between Włocławek and Toruń – notes Mariusz Adamusiński, Director of the Distribution Center in Brześć Kujawski.
An important point in optimizing the operation of LPP logistics facilities is reducing their impact on the environment. The warehouse in Brześć Kujawski is currently in the process of sustainable building certification under the BREEAM system. The facility is equipped with, among other things, a recuperation system in office areas, which allows for the recovery of up to 95% of heat. Furthermore, thanks to the installation of photovoltaic panels on the roof with a total capacity of 1.5 MW and an area of over 7,000 m2, the building is powered by renewable energy. LPP attaches great importance to employee comfort, which is why, already at the design stage of the distribution center, one of the priorities was to ensure the most favorable working conditions. Optimization of lighting, heating, air conditioning, and ventilation systems thanks to an advanced BMS system, as well as wide corridors and glazing of the warehouse, are just some of the available amenities. The company has also separated its own bus depot with 5 platforms and 17 parking spaces and created its own transport network, facilitating access to the workplace for people from surrounding towns.
– The Distribution Center in Brześć Kujawski is a modern facility, designed and built in accordance with our strategic assumptions. We are pleased that our efforts to date, supported by experience, have enabled the development of optimal logistics solutions while simultaneously fulfilling sustainable development goals – summarizes Sebastian Sołtys.
LPP, striving to achieve full operational capacity at the facility, continues the recruitment process for employees. Due to the infrastructure solutions applied in the distribution center, more specialists are needed, especially for the maintenance department, including electricians, electromechanics, and maintenance technicians.