Tunnel boring machine arrived in Poland with DB Schenker

Tunnel boring machine arrived in Poland with DB Schenker

In mid-October 2022, the unloading of the TBM machine for boring a tunnel on the S19 road construction site was completed at the port in Szczecin. This was one of several stages of a spectacular transport carried out by DB Schenker on behalf of the Mostostal Warszawa and Acciona Construcción consortium. The logistics operation began in the town of Noblejas. There, the TBM was dismantled by engineers, and its parts were divided based on weight and dimensions.

The heaviest load on Polish roads to date

The heaviest components, including the main drive and the cutter head, were transported by road by the Spanish branch of DB Schenker from Noblejas to the port of Santander, from where they arrived in Szczecin within a week after loading. The next stage is a journey by special barges along the Oder River to Opole. There, the machine components will be unloaded and secured on platforms consisting of self-propelled axles. Next, the transport will move by land to Babica. Lighter components will arrive from Spain to the Podkarpacie region directly by road transport.

A logistics challenge for experts

DB Schenker had been preparing for this demanding logistics operation for over 18 months. On the logistics operator’s side, a team of a dozen or so employees from the company in Poland and Spain, along with specialized carriers who are important partners in this project, worked on solutions to ensure the safe transport of the machine.

– Many factors were taken into account during the implementation of this undertaking. We are talking not only about regulations governing the transport of oversized loads. It also involved, for example, verifying the strength of bridges and viaducts, and examining the possibility of performing all necessary maneuvers with the special trailer on which the heaviest TBM components, weighing up to 230 tons each, are transported. – lists Tomasz Kwapis, Head of the Oversized Transport Department at DB Schenker. – All these variables influenced the decision on the type of transport, the route from Opole to Rzeszów, and finally the duration of the entire operation – adds Tomasz Kwapis.

73 meters long and 68 wheels

After unloading in Opole, the heaviest TBM components will be transported on a special mega-trailer, consisting of two platforms with self-propelled axles, which together have 68 wheels. The length of the entire set is 73 meters. To make the transport possible, it was even necessary to build a dedicated exit from the motorway for this operation, which will allow the platform to turn. In accordance with regulations, the transport will be carried out at night at a speed of 10 to 15 km per hour. The trailer will have to overcome 396 bridges, viaducts, and crossings on its way. All TBM components will reach Babica by the end of the year. There, the assembly of the machine will begin, which will take three months. The goal is to bore the tunnel, which will start in 2023.

The project is being carried out on behalf of the consortium of Mostostal Warszawa and Acciona Construcción, the contractor for the S19 expressway from the Rzeszów Południe junction to the Babica junction. The investor is the General Directorate for National Roads and Motorways. This is one of the most technologically difficult infrastructure construction projects in Poland.

TBM is impressive

The TBM is a powerful machine that will bore one of the longest tunnels in Poland, 2,255 m long, under the Grochowiczna hill in the Podkarpacie region. It will not only bore into the ground but simultaneously install special reinforced concrete elements that form the tunnel lining. The machine’s work pace is from a few centimeters per minute to about 10 m per day. The TBM weighs 4,300 tons, has a power of 12,000 kilowatts, a length of 107 meters, and a cutter head diameter of 15.2 meters. The machine was previously used in the construction of the Madrid bypass.