New quays are being built in the Szczecin port in the Kashubian Basin

Zarząd Morskich Portów Szczecin i Świnoujście SA

“Improving access to the Port of Szczecin in the area of the Kashubian Basin” is one of the flagship investment projects implemented by the Szczecin and Świnoujście Seaports Authority in the port of Szczecin. Its goal is to increase the port’s capacity for handling general and bulk cargo. The project also aims to increase the competitiveness of the port in Szczecin by improving access for merchant vessels with a larger tonnage than currently possible.

In the presence of invited guests, including Member of the Sejm of the Republic of Poland Leszek Dobrzyński and the West Pomeranian Voivode Zbigniew Bogucki, on March 22 of this year, at a special press conference, ZMPSiŚ SA, together with the contractor Korporacja Budowlana Doraco, announced the progress of work carried out as part of the investment.

Scope of work

The work includes the reconstruction of the most heavily used quays in the bulk cargo area, i.e., the Katowickie and Chorzowskie quays. Along with them, the Chorzowskie-Uskok and Gliwickie-Uskok quays will also be rebuilt. As part of the project, the work also includes the land reclamation of the Notecki Basin and the construction of the Zamykające Quay, as well as the construction of the Dąbrowieckie Quay with a dolphin berth nearly 290 m long, the casing of the corners of the Ostrów Mieleński and Mieleńska Łąka islands, and the deepening of the Kashubian Basin area to a depth of 12.5 m.

Project progress status

  • The financial progress of the entire contract is nearly 65 percent, while the physical progress is almost 68 percent.
  • The most advanced works are on the Dąbrowieckie and Gliwickie-Uskok quays, where work is nearly 100 percent complete.
  • The Notecki Basin has been completely closed – backfilling work of the basin is underway.
  • On the Chorzowskie and Chorzowskie-Uskok quays, pile driving, piling, reinforcement, and concreting works are underway; the completion of work on these two quays is planned for Q4 2023.
  • On sections 10-13 of the Chorzowskie quay, almost all types of work have already been completed. Final work related to the construction of the railway and road surface of the quay is underway.
  • On the Katowickie quay, sections 1-6, the sheet pile wall has been driven, and the yard layout has been completed. Reinforcement and concreting of the lower slab of the quay are underway.
  • Work related to strengthening the banks of the Ostrów Mieleński and Mieleńska Łąka islands has been almost entirely completed. In the meantime, dredging works in the basin are ongoing. The spoil is being deposited in reclamation fields located on Ostrów Grabowski and the Notecki Basin, which, after land reclamation, will create a land reserve for the development of port infrastructure in the area of the Zamykające quay. The completion of all work is planned for the third quarter of 2024.

Costs

The cost of the project is nearly PLN 223 million. The investment received PLN 150.2 million in EU funding from the Cohesion Fund under the Infrastructure and Environment Operational Program. After the completion of the investment, vessels with a cargo of 45-50 thousand tons on board and a draft of 11 m will be able to call at the port of Szczecin.

Basic parameters of the quays after the completion of the investment:

  • Katowickie Quay: length 502.12 m; technical depth 12.5 m.
  • Chorzowskie Quay: length 295.65 m; technical depth 12.5 m.
  • Chorzowskie-Uskok Quay with RO-RO ramp: length approx. 73 m, technical depth 12.5 m.
  • Gliwickie-Uskok Quay: length approx. 56 m, technical depth 12.5 m.
  • Dąbrowieckie Quay with dolphin berth: length 288.61 m; technical depth at the berth 10.5 m (stage I).