Construction works related to the modernization of the runway will take place at Poznań-Ławica Airport from April to October this year. This means significant limitations in the handling of flight operations, including the complete closure of the runway. This is a very important undertaking. The investment will certainly affect the safety of air traffic, but will it also contribute to expanding the offer of Ławica?
<\/strong><\/p>
Hanna Surma, Press Spokesperson for Poznań-Ławica Airport<\/strong><\/em><\/strong><\/em>: Poznań-Ławica Airport has finalized the operational aspects of the runway modernization, which is necessary due to current technical parameters and the requirements of ICAO (International Civil Aviation Organization). Construction work will last from April to October 2015. For technical reasons, it is necessary to temporarily close the runway around-the-clock, which is planned for the turn of September and October.
The runway modernization investment, planned since 2007 as part of the multi-annual airport expansion program, is aimed at improving the safety of flight operations. The preparation stages included assessing the technical condition based on research, as well as conceptual and design work. The timeline depends on the scope of construction work and technological requirements, as well as atmospheric conditions such as temperature and precipitation. The modernization will last from April to October 2015, but the greatest intensity of work is planned for early autumn. This means limitations in the handling of flight operations, including the complete closure of the runway. The work schedule provides for this between September 21 and October 11 of this year. During the months of peak passenger traffic, i.e., from mid-June to the end of August, work will be carried out outside the runway area, so it will be used normally during this time. In the remaining period of modernization, usage restrictions apply to nighttime hours. Passenger traffic handling during the complete runway closure depends on the carriers, who make autonomous decisions regarding the organization of their aircraft operations.
The necessity to carry out the modernization in 2015 stems from the degradation of the runway’s load-bearing capacity, which has been confirmed by research. According to calculations, the current state and continued operation will not allow for the handling of flight operations by the most popular Airbus A320 and Boeing 737 aircraft in the near future of 3-4 years. The effect of the modernization, in addition to solving the diagnosed technical problems, is to increase safety and comfort of use through: pavement reconstruction, construction of a new drainage system, construction of new navigation lighting (preparation for the introduction of Category II Instrument Landing System), and construction of an icing warning system. The modernization will also enable the handling of aircraft with increased weight, even with a larger number of take-offs and landings. This investment is co-financed by the European Regional Development Fund under the Wielkopolskie Regional Operational Program.<\/p>