Good pace of implementation of the National Railway Program

Good pace of implementation of the National Railway Program

10,000 employees and over 3,000 machines are involved daily in the implementation of the National Railway Program. PKP Polskie Linie Kolejowe SA are maintaining a good pace of investment despite the ongoing pandemic. 85% of the National Railway Program projects, worth PLN 76 billion, have already been completed or are currently at an advanced stage of implementation. Thanks to these investments, the railway is becoming more accessible, safer, and increasingly competitive.

– Investments under the National Railway Program, which increase the accessibility and capabilities of the railway both in the regions and on international routes, are being implemented at a good pace. With the new perspective, further tenders will be ready, which are already being prepared by PKP Polskie Linie Kolejowe SA – said Deputy Minister of Infrastructure Andrzej Bittel.
Every day, works worth over PLN 40 million are carried out on the railway network. In 2020, PLK plans expenditures at the level of over a dozen billion zlotys. Maintaining the continuity of investment implementation, announcing new tenders, and signing contracts allows for maintaining stability in the construction market.
– We are not slowing down and are continuing the implementation of the National Railway Program. Currently, we are carrying out works on construction sites with a total value of over PLN 51 billion. We have completed works worth approximately PLN 14 billion. This means that 85% of the NRP consists of projects completed or at an advanced stage of implementation – stated Ireneusz Merchel, President of PKP PLK SA.

The implementation of the NRP goes hand in hand with planning for the next perspective. In 2021, the PLK company will be ready to announce tenders for construction works for 26 investment projects worth approximately PLN 36 billion. Furthermore, in 2022, another 6 technical documentations will be ready for projects worth approximately PLN 11 billion. 33 documentations are currently being prepared for projects of the new European Union financial perspective, worth approximately PLN 93 billion.

Source: Ministry of Infrastructure

 