Excavation of the longest railway tunnel in Poland

Excavation of the longest railway tunnel in Poland

The “Jadwiga” TBM, weighing over 2,500 tons, has begun construction of a railway tunnel under Pisarzowa. Over the next year, a new structure nearly 4 km long will be built, which will shorten train travel between Limanowa and Nowy Sącz. This will be the first of 16 such structures planned as part of the “Podłęże-Piekiełko” project, the largest investment by Polish Railway Lines in the south of the country. The task is co-financed by the European Union under the National Recovery and Resilience Plan.

Excavation of the railway tunnel between Męcina and Mordarka has started. It is being carried out by the larger of the two tunnel boring machines working at this site. Jadwiga weighs over 2,500 tons and is 90 meters long. The machine and the specialists operating it face a significant challenge – exactly 3,750 meters of underground route must be completed. The structure, with a diameter of nearly 11 meters, will be built step by step with millimeter precision. Using a rotating head equipped with steel teeth, the TBM simultaneously excavates the soil and installs the concrete tunnel walls. In the background, heavy machinery and an industrial railway supporting them remove the excavated material, while transporting concrete wall segments, which are produced non-stop in a nearby prefabrication hall, in the opposite direction. The entire operation is planned for approximately 10 months of continuous work.

Railway workers and contractors face an ambitious task. The coming months will be hard work on the construction of the longest railway tunnel in Poland. I am glad that the investment is being implemented according to the adopted plan. Thanks to it, the region will gain new opportunities for economic and social development. – says Dariusz Klimczak, Minister of Infrastructure.

A total of two tunnels will be built under Pisarzowa. In addition to the facility for trains, the “Kinga” TBM has been building a smaller evacuation tunnel since the end of March. During this time, the machine has already completed 420 meters, and this number is growing day by day. These will be the first tunnels built for the “Podłęże-Piekiełko” project. In total, 20 such structures will be built as part of the largest investment by Polish Railway Lines in southern Poland. Trains will run in 16 of them, with a total length of nearly 21 km. The remaining 4 will be evacuation tunnels, and their length will reach approximately 10 km.

This is one of the most difficult projects currently being implemented by Polish Railway Lines. We are building tracks on a completely new route, in a very demanding environment. We are preparing for the implementation of subsequent sections of this largest railway investment in the south of the country. – says Marcin Mochocki, member of the board of PKP Polskie Linie Kolejowe S.A.

Modernization of the railway line

The longest railway tunnel in Poland, which will be built in the vicinity of Limanowa, is a fragment of the new route of railway line No. 104. The modernization of the Limanowa–Klęczany siding section is being carried out by a consortium of companies consisting of Budimex S.A./Gülermak Ağir Sanayi Inşaat ve Taahhüt A.Ş./Gülermak Sp. z o.o., and its cost is over PLN 1.9 billion. This is one of four parts of the “Podłęże-Piekiełko” project where construction work is already underway. The others are the Limanowa station and the Klęczany siding–Nowy Sącz and Chabówka–Rabka Zaryte sections. Tender procedures are underway for four other fragments of this line: Rabka Zaryte–Mszana Dolna–Fornale (Kasina Wielka), Szczyrzyc–Tymbark, Tymbark–Limanowa, and Podłęże–Gdów.

The “Podłęże-Piekiełko” project consists of the modernization and electrification of the 75 km Chabówka–Nowy Sącz route and the construction of a 58 km new line, ultimately connecting Podłęże with Tymbark and Mszana Dolna. As a result, a new connection will be created that will facilitate communication between Krakow and the Podhale and Sądecczyzna regions. The fastest trains will cover the Krakow–Nowy Sącz route in about 60 minutes. Meanwhile, the trip from the capital of Małopolska to Zakopane will take about 90 minutes. Fragments of this investment are financed under the National Recovery and Resilience Plan. More about the project: www.podleze-piekielko.pl

Source: PKP Polskie Linie Kolejowe S.A.