A client commissioned the transport of two pallets of goods. They did not choose a dedicated transport service with a guaranteed delivery date, but rather a standard transport service available in the carrier’s/forwarder’s service catalog. According to an email from a consultant on the carrier’s side, the shipment was supposed to arrive at the destination in three days. However, the shipment reached the recipient on the fourth day. Did a delay in transport occur?
Expert response: At first glance, the above question may seem illogical or at least trivial. After all, the carrier’s consultant indicated that the shipment should arrive in three days, and it arrived in four. It should therefore be obvious that a delay occurred in this case. However, this is not always the case. In legal language, including transport law, certain terms have the meaning assigned to them in an act, an international convention, or even in an agreement between the parties, or in the terms and conditions of service issued by one party and accepted by the other upon placing an order. Thus, the Polish Transport Law Act states that the carrier is liable for a delay in delivery. However, it does not define what we should understand by this term. It can be generally assumed that a delay is the carrier’s exceeding of the final deadline for the completion of transport. The CMR Convention is more precise and states that “A delay in delivery occurs when the goods have not been delivered within the agreed time-limit or, when there is no agreed time-limit, when the actual duration of the carriage having regard to the circumstances of the case, and in particular, in the case of partial loads, the time required for making up a complete load in normal circumstances, exceeds the time it would be reasonable to allow to a diligent carrier.” From practice, it can be pointed out that the deadline for the completion of transport is usually provided when placing an order. However, depending on how the conditions for the execution of such an order are shaped, as provided for, for example, in the carrier’s general terms and conditions of service, such a deadline may be a so-called “fix” deadline, i.e., a fixed one, or it may be defined as an “estimated” deadline. If, on the other hand, we do not agree with the carrier on a specific, non-negotiable deadline, and as in our query, we do not commission, for example, dedicated transport, the carrier may defend itself against the allegation of delay by pointing out that although the transport deadline was not met, one day of delay falls within the normal course of transport, as our two pallets had to be loaded onto another, larger transport. In such circumstances, what is an obvious delay for the client may not be treated as a delay under transport law.
Legal basis:
• Act of 15 November 1984 Transport Law
• Convention on the Contract for the International Carriage of Goods by Road (CMR) and Protocol of signature, done at Geneva on 19 May 1956
Legal status of the publication (date): 2017-07-24