The Port of Gdańsk has commissioned two renovated quays as part of the ongoing project to revitalize the port’s quays and fairway. The opening ceremony for the revitalized Mew and Obrońców Poczty Polskiej quays took place on November 15, 2019.
The first stage of the expansion of the Obrońców Poczty Polskiej Quay involved the reconstruction of half of its length. The remaining part of the quay still requires renovation. It is planned to be extended by 46 meters. Increasing the technical depth to 11.2 meters now allows for the handling of vessels with a greater draft than before. Currently, the quay is used mainly for handling aggregates, heating and base oil, and sulfur. Two vessels can be handled here simultaneously.
Following the modernization, the Mew Quay has gained a mooring function. Small vessels with a draft of up to 5.3 meters can dock here.
– The implementation of Stage I included construction works over a total length of 286 meters, including the construction of 174 meters of the Obrońców Poczty Polskiej Quay and 112 meters of the Mew Quay. Completing the work on time is the result of good cooperation between the General Contractor, the Contract Engineer, and the Employer. It also allows the operator to use the quay without disruption and to move work to Stage II – says Marcin Osowski, Vice President of the Board for Infrastructure.
The value of the investment completed in Stage I is over PLN 26 million. Stage II, which will cost PLN 16 million, involves the complete renovation of the Obrońców Poczty Polskiej Quay. The expected final completion date for work on this section is the end of 2020. The total value of the investment is over PLN 40 million. Stage I included construction works involving hydrotechnical structures, road surfaces, storm water drainage systems, water supply, electrical networks, lighting, reconstruction of crane beams, and dredging works with bottom reinforcement. The work schedule was adjusted to the frequency of transshipments carried out at the terminal, causing no downtime in the operations of other companies. The general contractor for the construction works is DORACO.
– The implementation of the OPP and Mew Quays was one of the most demanding hydrotechnical projects carried out by DORACO – these are the words of Radosław Preiss, a member of the DORACO board. – The location of the historic Mewi Szaniec (Seagull Rampart) at the Mew Quay required us to use additional surveys and constant geodetic monitoring, as well as special piling technology to prevent soil destabilization and thus damage to the facility.
The investment was carried out as part of the project “Modernization of the fairway, expansion of quays, and improvement of navigation conditions in the Inner Port in Gdańsk,” which assumes investments totaling over EUR 110 million. The project involves the reconstruction and modernization of a total length of approximately 5 km. Thanks to the implementation of these investments, navigation conditions at the Port of Gdańsk will improve.