EC Nowa Sp. z o.o. is a plant separated from the structure of Huta Katowice, providing energy utilities necessary for steel production. The contract with PKP CARGO was signed until the end of 2010.
– This is another significant step on the path to rebuilding our market position. We have not delivered coal to EC Nowa for approximately twenty years, and the power plant was serviced by private carriers – emphasizes Marek Zaleśny, member of the PKP CARGO management board for commercial affairs.
Transport to EC Nowa will be carried out mainly from mines belonging to the Katowice Coal Holding. Approximately 60 percent of the volume delivered to the power plant will be dispatched from the “Murcki” coal mine, where PKP CARGO has also been operating a railway siding since last year.