GSM-R on the railway will enable voice communication

GSM-R on the railway will enable voice communication

Still in 2025, Polskie Linie Kolejowe S.A. will enable communication between train drivers and traffic controllers using the GSM-R system. From the beginning of September to the end of October, digital communication is being tested on the Gdańsk – Warsaw line section. Subsequently, the implementation of digital communication is planned for 1,500 km of railway lines.

The GSM-R system has been operating on the Polish railway for several years. However, its use is focused only on sections where the ETCS Level 2 system has been built, and it is used for the exchange of digital data transmitted via radio from local control centers to onboard computers in trains.

From September 1, 2025, Polskie Linie Kolejowe S.A. began observed operation (which can be simplified as testing) of GSM-R on an approximately 250 km section of the Warsaw – Gdańsk railway line in the area of communication between the train driver and the traffic controller. This means that old analog devices are no longer used, and modern terminals installed in passenger and freight trains as well as at traffic controllers’ stations are used instead.

Technically, we were well prepared to start observed operation for GSM-R on the Warsaw – Gdańsk line. Now we are focusing on testing procedures, checking instructions, and communication rules in the digital version. We receive comments from carriers every day, but so far none of them have concerned the technical area. All comments concerned the use of the system – said Krzysztof Waszkiewicz, member of the Management Board of PKP Polskie Linie Kolejowe S.A. responsible for infrastructure maintenance.

To begin observed operation, since the middle of last year, Polskie Linie Kolejowe S.A. had to perform a number of necessary technical tasks – from configuring a new control center for the GSM-R system, through reconfiguring and connecting base station devices to this center, to enabling international roaming and replacing SIM cards in receiving devices. During this period, the infrastructure manager worked closely with carriers, conducting consultations with them regarding necessary regulations, procedures, training meetings, and test runs. Checking connections began after the holiday season so as not to restrict traffic during the period when the line is most heavily loaded with transport, in case of any irregularities.

The tests will last until the end of October 2025. Then, in November, there will be time to develop conclusions from the observed operation. These may be helpful in improving procedures related to the use of the GSM-R system.

PLK SA plans to cover approximately 1,500 kilometers of railway lines with the GSM-R system in the near future, including selected railway lines as early as mid-December.

Source: PKP Polskie Linie Kolejowe S.A.