General Contractor HARDEN CONSTRUCTION has started construction of Panattoni Park Będzin with a total area of 89,000 sqm. A complex consisting of two warehouse, service, and production halls will be built on a 20-hectare plot located in Będzin.
HARDEN CONSTRUCTION has commenced work on the construction of the Panattoni Park Będzin facility. The warehouse complex is located in Będzin in the Silesia region and will consist of two warehouse, service, and production halls. The facility is being implemented under a design-and-build formula.
Currently, work is underway on the construction of a hall with an area of 27,500 sqm. The site was accessed at the beginning of March, and the planned completion of construction is the fourth quarter of this year.
Panattoni Park Będzin is located by national road No. 86, which places the facility in the very center of the Upper Silesian Conurbation near the country’s main transport routes. One of them is the A4 motorway running from the German border to the Ukrainian border. Nearby is also the A1 motorway connecting the south of Poland with the north. Such a good location of the facility, including its proximity to an industrial zone, also brings challenges.
Harden Construction encountered a number of challenges during construction
As part of the complex’s construction, it was necessary to plan a buffer parking area for waiting deliveries. This is intended to prevent blocking national road No. 86, where there is heavy traffic.
Furthermore, Panattoni Park Będzin is located over the Psarski Stream. As a result, a road culvert will be built over the watercourse between the buildings. This is a necessary investment that will ensure proper access.
The construction of the facility poses a number of challenges for the general contractor, HARDEN CONSTRUCTION. The proximity of the Psarski Stream means that the area is under environmental supervision. This makes it necessary for an ecologist to prepare a monthly report that determines the impact of construction on the natural environment. In addition, due to geological conditions, constant supervision by a geologist is necessary, as the area was subject to shallow mining in the past, which affects soil and water conditions.
– Ecological and geological supervision is one thing. But in addition, the construction is under constant zoological supervision so that the investment has the least possible impact on the natural environment. Nevertheless, for HARDEN CONSTRUCTION, minimizing interference with the natural environment is just as important as delivering the highest quality industrial space. All this, combined with a short completion deadline, makes the construction of Panattoni Park Będzin a major challenge – says Łukasz Kozerski, Chief Operating Officer at HARDEN CONSTRUCTION.
The aforementioned mining activity and the proximity of the Psarski Stream mean that there is a high groundwater level at the construction site. Additionally, a high-voltage network runs close to the investment site. Due to such close proximity, agreements with the transmission network operator are necessary.
– Due to a very tight schedule of activities and difficult working conditions, we try to minimize emerging risks. For this reason, deliveries of prefabricated elements were divided among six plants. The implementation of successive scopes of work is carried out using the lean management formula, which allows us to meet short deadlines. As professionals, we face demanding projects every day and take on new challenges without fear, including ones such as Panattoni Park Będzin – comments Łukasz Kozerski, Chief Operating Officer at HARDEN CONSTRUCTION.
The building will not only interfere with the natural environment to the smallest possible extent, but it must also be as sustainable as possible itself. Therefore, some materials used for the construction of the warehouse will have EPD certification, and materials from suppliers must meet the ISO 14001 standard. In addition, bicycle shelters and electric car chargers are planned, and the roof will be adapted for the future installation of a photovoltaic system. BREEAM certification at the Excellent level is also planned.
Source: Harden Construction