“Karpatka” to bore a 2 km tunnel under Rzeszów

Karpatka to bore a 2 km tunnel under Rzeszów

The final components of the TBM (Tunnel Boring Machine), which will bore a 2.2 km long tunnel on the S19 Rzeszów Południe-Babica expressway, have already arrived at the construction site in Babica. Once assembled, the machine will weigh 4,000 tons and reach 112 meters in length. The cutterhead of “Karpatka” has a record-breaking diameter of 15.2 meters.

In February, the assembly of the machine’s components into segments will begin. Special crawler cranes with a lifting capacity of 300 to 650 tons will assist in this process. The investment, carried out by a consortium of Mostostal Warszawa and Acciona Construcción, is a significant engineering challenge. The record-long tunnel will be constructed using the most modern technology available, i.e., using TBM equipment rather than the mining method. This allows for work to be completed faster and much more safely.

– The construction of the S19 expressway section from the Rzeszów Południe junction to the Babica junction is the most advanced task we are carrying out for the General Directorate for National Roads and Motorways. The scale of the construction, the technology, the know-how, and the specialized TBM equipment are incomparable to most investments currently being designed and implemented in Poland – says Jorge Calabuig Ferre, Vice President of the Management Board of Mostostal Warszawa. – Taking on such an interesting and at the same time technologically difficult construction project is a sign of the development we have made in recent years, as well as a confirmation of our strong position as a leading General Contractor for infrastructure investments in Poland.

Along the entire length of the tunnel, there will be 32 alarm points, 28 emergency niches, and 28 hydrants. The tunnel will be equipped with transverse ventilation. Fresh air will be supplied from below along the entire length of the tunnel, and exhaust air will be discharged through special portals.

– Success in the implementation of such a technologically advanced investment is primarily due to the staff of the best engineers from Mostostal Warszawa and Acciona Construcción, who at this important and difficult stage are demonstrating professionalism, immense commitment, and attention to the quality of work – says Sławomir Barczak, Director of the Infrastructure Area at Mostostal Warszawa.

As part of the investment – in addition to the tunnel – six flyovers, two viaducts, a grade-separated crossing along national road No. 19, and an underpass beneath the S19 route will also be built. On the section from Rzeszów to Babica, three animal crossings will be constructed.