Contractual penalties should protect the interests of the ordering party, but they are sometimes used as a way to cut costs or generate additional income at the expense of contractors. Although contractual penalties in transport orders are very common in the TSL industry, the legitimacy of many of them is questionable, and some, in the light of the law, border on the absurd.
A transport order is a very important document that defines the terms of cooperation between the carrier and the ordering party for the performance of transport services. Precisely defining the rights and obligations of the parties in this document is a safeguard against unpleasant legal and financial consequences. In addition to standard elements such as the ordering party’s details, carrier’s details, transport costs, or the type of goods transported, various types of contractual penalty clauses are also encountered.
What are contractual penalties?
Contractual penalties are a tool for seeking compensation in the event of non-performance or improper performance of specific obligations contained in a contract. As explained by Maurycy Kieruj, legal counsel at TC Kancelaria Prawna, in accordance with the Civil Code, obligations subject to such a penalty should be clearly indicated in the contract:
- It is particularly necessary to specify the amount of the contractual penalty or the criteria based on which it will be determined. The penalty must therefore be set in advance or constitute a percentage calculated based on, for example, the value of the goods or the contract amount. The contractor may also set a contractual penalty for delay in executing the order in the form of a specific percentage of the agreed contractual remuneration for each day of delay, even if the final deadline for calculating the contractual penalty or its maximum amount has not been specified.
Contractual penalties versus regulations
In the context of the specific nature of transport law and the CMR Convention for determining liability for the proper performance of a transport contract, one more important issue related to contractual penalties must be mentioned – in accordance with Art. 473 § 1 in conjunction with Art. 353(1) of the Civil Code, the parties may contractually extend the debtor’s liability.
– This principle also applies to contractual penalties – according to it, the parties may extend or narrow the scope of the contractor’s liability, and thus primarily indicate additional circumstances for which they will be liable, and consequently – which of them, in the event of a breach, may result in the imposition of a contractual penalty – says the legal counsel of TC Kancelaria Prawna and adds:
This principle does not quite work in transport law and the CMR Convention. The Convention in Art. 41 states directly that any clause which would directly or indirectly infringe the provisions of this Convention shall be null and void. Extending the carrier’s liability (usually implemented precisely through clauses containing contractual penalties) cannot therefore provide for more severe liability than the mandatory provisions of the law. Contractual penalties, as a rule, are not excluded for breaches not provided for in transport law and the CMR Convention. And this is where the field for the creativity of transport ordering parties appears.
Absurdities from contractual clauses
Detailed terms of transport orders are sometimes riddled with provisions containing contractual penalties. They are not always a reflection of the significant interests of the ordering parties – sometimes they are just a pretext to “skim off” part of the payment for transport. Even if they do not raise doubts from a formal point of view, contractual penalties are not always effective and enforceable. The expert from TC Kancelaria Prawna points out that this will happen when the reservation of a penalty constitutes an abuse of the creditor’s right, its amount is grossly excessive, the breached obligation is insignificant in the context of the entire contract, and the creditor does not suffer any damage due to its non-performance.
Such contractual penalties sometimes border on the absurd, as shown by the examples below.
Example 1
The contractor also undertakes to ensure that the driver (as a representative of the Ordering Party before clients) behaves culturally and professionally both at the places of loading and unloading of goods and in the immediate vicinity of these places. Violation of the obligations indicated in this point entitles the Ordering Party to impose a contractual penalty on the Contractor in the amount of the agreed freight.
A driver’s cultural behavior is difficult to classify as an additional obligation to a transport contract. Moreover, this is a very subjective circumstance, hence such a contractual penalty should be considered ineffective.
Example 2
The contractor is obliged to ensure that the driver performing the transport has a functional mobile phone, enabling direct contact with the driver and sending and receiving MMS messages. In the event of no contact with the driver performing the contract on behalf of the Contractor for a period longer than 30 minutes, the Ordering Party has the right to demand from the Contractor payment of a contractual penalty in the amount of 100 EUR and 50 EUR for each subsequent 30 minutes.
Also, such an obligation – for the driver to have a functional phone with them – is certainly not the essence of a transport contract. And although a contractual penalty does not have to be reserved for the performance of elements that are objectively essential to the order, in this case, the nature of the breach does not justify such a high penalty.
Example 3
In the absence of an obligation to exchange pallets/gitterboxes (at loading or unloading or both), the Contractor undertakes to collect at the place where there was no obligation to exchange (or another place indicated in the order) an original pallet receipt or other appropriate document confirming that the exchange of pallets/gitterboxes did not take place. Failure to provide documents confirming that the exchange of pallets/gitterboxes did not take place within 24 days from the date of service performance will result in the calculation of a contractual penalty in the amount of 16.00 EUR per pallet and 100.00 EUR per gitterbox (equivalent in PLN according to the NBP average exchange rate on the date of issuing the debit documents).
In this case, the transport order is supposed to show the lack of an obligation to exchange pallets/gitterboxes. Despite the lack of an obligation to exchange the aforementioned means of transport, the carrier, under the threat of a contractual penalty, is to prove the lack of such an exchange. Negative circumstances do not require proof. Such a contractual penalty should be considered ineffective.
Example 4
In the event of (…) limited liability company with its registered office in G. being charged a penalty by a client, the carrier is obliged to pay it in the amount requested by the client, and in the event of damage exceeding the value of the freight, compensation in the full amount. In the event of failure to provide the required vehicle on time or failure to meet another deadline or obligation resulting from the order, (…) limited liability company with its registered office in G. – regardless of other claims – has the right to charge the carrier a contractual penalty in the amount equivalent to 150 euros for each started day of delay; in the event of higher damage – the amount of full compensation. Until the amount of damage is determined, the ordering party has the right to withhold payment of remuneration for services.
The reservation by the parties in a transport order of a contractual penalty for delay in the delivery of goods to the extent that it constitutes a “failure to meet another deadline resulting from the order” is contrary to the applicable provisions of the law. We are talking about the provisions contained in the CMR Convention, which are mandatory. The issue of compensation for delay in the delivery of goods is regulated by the provisions of this convention, and therefore contractual provisions in this regard are invalid.
– In accordance with the content of Art. 23 paragraph 5 of the CMR Convention, in the event of delay in delivery, if the entitled person proves that damage resulted from this, the carrier is obliged to pay compensation which cannot exceed the amount of the carriage charge, and higher compensation can only be claimed in the case of declaring the value of the goods or declaring a special interest in their delivery, in accordance with Articles 24 and 26 of the Convention. According to the content of Art. 30 paragraph 3 of the Convention, delay in delivery may constitute a basis for compensation only if the reservation was made in writing within 21 days from the date the goods were placed at the disposal of the consignee – explains Maurycy Kieruj, legal counsel at TC Kancelaria Prawna.
Beware of pitfalls in contractual penalties
Contractual penalty clauses in transport orders must comply with the provisions of national or international transport law and the Civil Code. It is important to carefully read the content of this document before signing it, especially if it refers to the possibility of incurring financial consequences. If the provisions of the order clearly violate the interests of one of the parties, this must be reported and corrected as soon as possible.
One should also not be afraid to consult contractual penalty clauses in transport orders with lawyers. Then we can be sure that they will be in accordance with the regulations, which can protect us from unnecessary disputes or be a guarantee of payment of compensation in the event of non-performance or improper performance of an obligation.
Source: TC Kancelaria Prawna