Port of Gdynia awaits final redevelopment

T. Urbaniak, Port Gdynia

A contract has been signed for the redevelopment of the Port of Gdynia’s internal basins to a depth of 16 meters. This is the final stage of multi-year investments carried out by the Port of Gdynia Authority. The investment is crucial for the further development of the port.

– The primary goal of this project is to enable the largest vessels in the Baltic Sea to call at the port. The implementation of the project will contribute to a fuller utilization of the port’s potential, an increase in transshipment levels at the terminals, and thus will increase the competitiveness of the Port of Gdynia in the Baltic Sea region – says Jacek Sadaj, President of the Port of Gdynia Authority S.A.

In recent years, the Norwegian, Slovak, and Italian Quays have been redeveloped, the Northern Pilot Spur has been shortened, and the redevelopment of the Pilot Spur and the Port Quay is currently underway. The above projects were aimed at enabling the execution of construction works critical to the port’s development, consisting of dredging works along the entire length of the Port Channel, from the Main Entrance to the Puck Quay, to a target depth of 16 meters. Basins III, IV, and V will also be deepened to the necessary extent. As part of the works, bottom reinforcements will be carried out at the Swedish, Bulgarian/Puck Quays, and over fuel pipelines located on the seabed in the Outer Port area; telecommunication cables running under the bottom of the Port Channel to the Navy area will be relocated. Approximately 4 million cubic meters of spoil will be dredged as part of the works, which will be deposited at a sea dumping site. The amount of spoil would be enough to fill 1,600 full-size Olympic swimming pools.

Investment map

The contractor, the Belgian company JanDeNul, is obliged to complete the subject of the contract within 16 months from the date of handing over the construction site. The implementation of the task is intended to enable the handling of significantly larger vessels up to 400 meters in length, which will significantly contribute to increasing transshipments at the Port of Gdynia, both in terms of containers, as well as bulk and general cargo.

Source: Port of Gdynia