Volkswagen Poznań launches an automated warehouse for smaller automotive components

Volkswagen Poznań launches an automated warehouse for smaller automotive components

The construction of an automated warehouse for smaller parts and components in hall 44 was the final stage in fully utilizing the new logistics areas created for the launch of the Volkswagen Caddy 5 production. Investments began in January 2021, and after just twelve months, the new warehouse was operating at full capacity.

On an area of approximately 1,200 square meters, about 43,000 KLT containers and cartons can be stored on racks over 9 meters high. The remaining 3,000 square meters of space are occupied by conveyor lines, goods receiving and dispatch zones, and an empty container storage area.

Processes in the new warehouse are highly automated. Four stacker cranes operate inside. Each of them moves at a speed of over 6 meters per second. The system also uses an innovative solution – the Twister cart, which can move up to four of the smallest containers in the rack simultaneously. Thanks to this, the efficiency of the processes and the warehouse itself has increased significantly. It now holds 43,000 containers compared to 37,000 in the previous external warehouse. During the conceptual phase, the possibility of further expanding the warehouse with a fifth stacker crane was also taken into account.

– The newly launched AKL warehouse is located in the immediate vicinity of the assembly halls, where most of the parts stored here are delivered, which is a huge benefit in terms of supplying components necessary for production – says Dietmar Mnich, Chairman of the Board of Volkswagen Poznań. – We are now able to react faster to the needs of the assembly lines and are not exposed to potential disruptions in the delivery of parts between the plant in Poznań Antoninek and the external warehouse.

Previously, the warehouse was located in Swarzędz – Jasin. To ensure continuity of supply, trucks operated on a shuttle system between Swarzędz and plant No. 1 in Poznań – Antoninek. Today, thanks to the launch of the warehouse directly on the plant premises, it has been possible to eliminate as many as 14 shuttle trips per day, which translates directly into a reduction of carbon dioxide emissions into the atmosphere by as much as 45.85 tons per year.