Finishing works are underway at the new LPP Distribution Center in Brześć Kujawski. As part of the implementation of environmentally friendly solutions, 4,000 photovoltaic panels have been installed on the building’s roof. The installation, with a total capacity of 1.5 MW and an area of over 7,000 square meters, is one of the largest pro-ecological projects in the region. In line with its sustainable development strategy, the new LPP logistics facility is designed to meet high environmental standards – the Polish manufacturer is focusing on, among other things, solar energy, emission reduction, and employee comfort.
LPP, a Polish clothing manufacturer, began construction of its largest logistics investment in January of this year – the Distribution Center in Brześć Kujawski, with operational activities scheduled to begin in the first quarter of 2022. The work schedule includes the implementation of a number of solutions aimed at reducing the center’s environmental impact, including the installation of photovoltaic panels.
– Harvesting solar energy for the needs of the distribution center is a pioneering project for LPP. We want our logistics facilities to be friendly not only to employees but also to the environment and local communities, which is why we are equipping them with increasingly advanced CO2 reduction systems and solutions that limit water and energy consumption. We hope that during the operation of the installation, we will learn its benefits in practice and be able to make decisions regarding similar solutions in our subsequent facilities. We also do not rule out further expansion of the photovoltaic installation at the newly emerging Distribution Center in Brześć Kujawski – comments Łukasz Piwoński, Administrative and Technical Director at LPP.
Photovoltaic panels have covered half of the roof of the new LPP logistics facility. They currently occupy over 7,000 square meters of space. The remaining part of the roof is prepared for potential further expansion of the PV installation.
– Usually, about 20 photovoltaic panels are installed in single-family homes. There are 4,000 of them on our building – it is as if 200 households in the region started using green energy, thereby reducing their draw from less ecological sources – adds Łukasz Piwoński.
The energy potential of the panels at the LPP investment site in Brześć is over 1,500 megawatt-hours per year. This means that such an installation could meet the annual energy needs of approximately 800* households. The installation of the Polish clothing manufacturer will serve as a source of renewable energy for the facility, while the surplus energy will feed into the power grid.
At the LPP Distribution Center located in the Brześć Economic Zone, the company also plans to introduce other environmentally friendly solutions, such as a recuperation system in office rooms, which will allow for the recovery of up to 95% of heat. The building also features an advanced BMS (Building Management System), which allows for the functional integration of automation modules, monitoring elements for equipment operation and energy consumption, as well as the facility’s technical installations: lighting, heating, air conditioning, and ventilation. The facility will also be equipped with a progressive LED lighting system that adjusts light intensity to weather conditions and the time of day – to ensure interior work comfort while maximizing energy consumption reduction.
*Statistics Poland (GUS) data: In 2019, electricity consumption per consumer (household) in Poland amounted to 1,963.9 kWh.
Source: LPP