The modernization work lasted 28 months. 52 km of tracks with subgrade and drainage were replaced, along with 50 km of overhead contact lines and supporting structures. The modernization also included the Chotyłów station. Among other things, underpasses were built there. Furthermore, four passenger stops were rebuilt in the towns of: Ogrodniki, Perkowice, Dobrynka, and Kobylany. The surface of 11 railway crossings was also rebuilt, as well as 9 bridges and 11 smaller engineering structures (culverts). Several kilometers of service roads parallel to the railway lines were also built, serving, among others, local residents. Railway traffic control devices and telecommunications network equipment were also upgraded. The non-traction power line, used for purposes such as platform lighting and powering equipment at railway crossings, was also rebuilt. The result of these modernizations is: the elimination of speed restrictions, a reduction in the operating and maintenance costs of the railway line, improved safety at railway crossings, enabling passenger trains to travel at 160 km/h and freight trains at 120 km/h, a reduction in travel time on the section from Siedlce to Terespol by approximately 40 minutes, a reduction in noise and vibration, and a decrease in the railway line’s impact on the natural environment, particularly on the migration of small animals. The task was carried out under contract ISPA/FS 2001/PL/P/PT/012-04 Lot D Biała Podlaska – Terespol by a consortium of companies: Przedsiębiorstwo Robót Kolejowych i Inżynieryjnych S.A. based in Wrocław, Przedsiębiorstwo Robót Komunikacyjnych – 7 S.A., Przedsiębiorstwo Robót Komunikacyjnych w Krakowie, Torpol sp. z o.o., Dolnośląskie Przedsiębiorstwo Napraw Infrastruktury Komunikacyjnej DOLKOM sp. z o.o., Pomorskie Przedsiębiorstwo Mechaniczno-Torowe sp. z o.o., and Przedsiębiorstwo “AGAT” S.A. The total cost of project No. ISPA/FS 2001/PL/16/P/PT/012 “Modernization of the E20 railway line on the Siedlce – Terespol section, Stage I” is 263.5 million euros. Eligible costs amount to 211.2 million euros, including: ISPA/FS grant of 158.4 million euros, and the state budget of 52.8 million euros. Stage II of the investment provides for, among other things, the modernization of the Siedlce, Łuków, and Międzyrzec Podlaski stations (in full scope of work) as well as further replacement of railway traffic control systems and telecommunications equipment. The commencement of work under the second stage is expected in the fourth quarter of 2010.