The expansion of the Poznań plant took 2 years. During this time, the welding shop was expanded and a new logistics hall was built. The investment cost PLN 2 billion and will be used for the serial production of a new model – the new generation Caddy 5.
– We have completed about 90 percent of all investments related to preparing the plant for the production of the new model. Currently, test vehicles are being produced, and before the start of serial production in September this year, we are planning the final reconfiguration of the plant for the new Caddy. Production will develop gradually, from several dozen units in the initial phase to full production capacity, which we will reach in 2021 – said Dietmar Mnich, Chairman of the Board of Volkswagen Poznań and Director of the Poznań plant.
The expansion of the factory began with the integration of factory areas that were separated by a public road. Subsequently, a new logistics hall with an area of 46,000 sq m was built, which will accommodate 10,000 containers with parts for the production of Caddy and T6.1. The biggest challenge of the investment, both financial and organizational, turned out to be the expansion of the welding shop. The company invested huge resources in a new hall with an area of over 14,000 sq m and a volume of nearly 200,000 cubic meters, as well as in modern technology. 450 multifunctional robots were purchased for production needs. Their task will be the precise construction of the Caddy 5 body, the structure of which has been reinforced with high-strength steel and hot-stamped steel. Proper processing and welding of these materials requires the use of durable, specialized equipment with increased pressure force. Robotization and automation require employees to have the skills to operate new equipment, which is why specialized staff training is part of the investment.
– Such far-reaching technological changes are always accompanied by equally significant organizational changes. With progress, new needs and new competencies emerge. Building the new Caddy 5 body will require performing significantly fewer manual tasks, while our demand for machine and equipment operators will nearly triple. In the case of the Poznań plant, over the last two years, we have carried out over 1,800 training sessions worth over PLN 3 million, aimed at retraining employees and preparing them to work in new conditions and in a new role – says Jolanta Musielak, Member of the Board for HR and Organization.
{youtube}https://www.youtube.com/watch?v=52g-hAFXCNo{/youtube}
Source: Volkswagen Poznań