For eight months, work has been underway at the Port of Gdansk on the expansion of the road and rail system in the Outer Port. The general contractor for the works is the Sopot-based company NDI, which, despite the winter season, has already achieved over 35% progress. A symbolic “topping out” ceremony has already taken place on one of the four road viaducts.
The WD-4 viaduct is the most advanced of the four viaducts under construction. Ultimately, it will carry traffic for the expanded dual-carriageway Kontenerowa Street. It runs over the railway network tracks in the Outer Port. Its span of 17.44 m is adapted to the location of the tracks that will be situated beneath it. The length of the structure is 41.10 m. The viaduct will be illuminated, and in addition to the roadways, there will also be a pedestrian and bicycle path to facilitate communication.
The viaduct was designed as two single-span structures with a deck made of prefabricated T-type prestressed beams. The construction used, among other things, 1,300 cubic meters of concrete and 210 tons of steel. The viaduct was built from 24 installed beams, each 18 meters long and weighing 12 tons. The beams were positioned using a 100-ton capacity crane with an accuracy of up to 1 cm.
Due to difficult ground conditions, the WD-4 bridge structure was founded indirectly on nearly 20-meter piles topped with a pile cap. Its construction required the relocation of existing underground utility networks.
– During the first 8 months of implementation, we focused our efforts on ground reinforcement works, earthworks, demolition of old and construction of new engineering structures, relocation of conflicting utilities, and construction of new utility networks that will allow for the modern functioning of the road and rail system at the Port – says Jacek Szymański, project director at NDI. – We have already reinforced 70% of the ground, and the installation of the structural elements of the deck slab for the next structure, i.e., the WD-2 viaduct, is planned for May.
In the coming months, NDI will continue network and earthworks, and surface works will also begin, both in asphalt and concrete technology, as well as track laying.
Backfilling around the structures will commence, which will allow for the laying of surfaces on the structures and their access roads in a short time, followed by their handover for use.
– I am very pleased with the progress of the work we are observing on the project. In mid-November last year, we laid the cornerstone for this facility, and today the topping out ceremony has already taken place. The pace of work is all the more satisfying because we have to plan our actions very precisely, ensuring full accessibility and operational capability of the Port – says Małgorzata Winiarek-Gajewska, President of the Management Board of NDI SA.
As part of the project to expand the road and rail system in the Outer Port, carried out by NDI for the Port of Gdansk Authority, the following streets are being rebuilt: Portowa, Poinca, Kontenerowa, and Budowniczych Portu Północnego, with a total length of 5.6 km. 4 new viaducts are being built, and 2 existing ones will be demolished (including one over active railway tracks and another over a complex of fuel transmission pipelines belonging to PERN, LOTOS, and Naftoport). An additional track to the DCT terminal, new tracks to coal terminals, and a modern railway traffic control system will appear. A buffer parking lot for trucks will also be created – the first in this part of the Port.
– The road and rail system is a key investment for the Port of Gdansk. Our contractors are developing dynamically, handling more cargo year by year, which must be transported efficiently. As the owner of these areas and port infrastructure, we must respond to these needs. We are very pleased with the pace adopted by NDI. We will see the final effect of the ongoing work next year, when all projects with EU co-financing are completed – explains Łukasz Greinke, President of the Port of Gdansk Authority.
The new 9.4 km long road and rail system (including 16 new turnouts) is also intended to serve as a base for the future Central Port, thanks to which the transshipments of the Port of Gdansk could reach 100 million tons per year. The value of the contract is almost 176 million PLN. The project will be completed by the end of 2020.