A thorough modernization of the PKP Energetyka catenary maintenance train fleet, which has been underway since 2018, is ongoing. By 2025, 80% of the fleet will meet the most modern standards, and its value will exceed half a billion PLN.
The catenary maintenance train modernization program was implemented to even more effectively carry out activities in the area of maintaining the overhead contact line for the company’s clients, primarily the railway infrastructure manager, PKP Polskie Linie Kolejowe. The modernized machines are more functional, safer, and allow for a significant increase in the comfort of daily work for the crews operating them across Poland.
– We are consistently implementing investments in our rolling stock. In just a few years, we will have one of the largest and most modern fleets of catenary maintenance trains in Europe. The result is an increase in safety, efficiency, and the comfort of our employees’ work. By modernizing the catenary maintenance trains, we are even better preparing for the challenges associated with the development of the railway – both the investments of PKP Polskie Linie Kolejowe and the Central Communication Port. It is worth emphasizing that the program is also about environmental protection – a smaller carbon footprint due to both the process of modernizing the existing fleet itself, as well as its daily operation – summarized Wojciech Orzech, CEO of PKP Energetyka.
The catenary maintenance train fleet modernization program is in line with the responsible business strategy implemented by PKP Energetyka regarding environmental care. Modernizing one train saves an average of 50 tons of waste and avoids the emission of 200 tons of CO2 that would be necessary to produce a new train. Furthermore, as part of the project, the life cycle of the machines is extended, which allows for the reuse of over 2,000 tons of metals and other components.

New vehicle standard
Each train being modernized is disassembled into approximately 10,000 parts, each of which is inspected and renewed or replaced. The most important changes are:
- transferring the drive from mechanical to hydrostatic, which provides greater cushioning and smoothness of vehicle operation,
- installing new-generation equipment, including: electrical, automation, and hydraulic systems. 100% of the installations are replaced,
- expanding diagnostic and monitoring systems,
- renewing the cabin, platforms, bogies, cranes, and correctors. In this process, their components are replaced to modernize and standardize the equipment,
- increasing work comfort through LED lighting and air conditioning,
- on selected trains, including those in Łódź and Zduńska Wola, innovative predictive solutions are being tested that monitor the probability of train system failures in real-time and perform systematic network measurements.
Modernization also means standardization. As a result, the company reduces parts storage and ensures faster and more efficient service, which in turn increases the quality of the traction services provided.
During the modernization, the knowledge and experience of employees and the railway-construction potential of the PKP Energetyka Capital Group are utilized. Repairs take place in the halls of the plants in Strzemieszyce and Słotwiny. The metamorphosis of one machine is several months of work by a team of nearly 100 people, coordinated by 30 of the company’s engineers and fitters. Thanks to the implementation of the program, the value of the PKP Energetyka catenary maintenance train fleet will increase to over 0.5 billion PLN.