Power restrictions and power generators in warehouses

Power restrictions and power generators in warehouses

Entrepreneurs have received letters from electricity suppliers warning of the possible need to limit power consumption. In some cases, these are drastic – by several hundred percent. Energy supply restrictions may mainly affect industrial and logistics facilities. Companies that do not comply face high penalties – up to 15% of their annual revenue. This is causing an increase in interest in power generators, the cost of which is rising rapidly while availability is falling.

Since the end of last year, entrepreneurs across Poland have been receiving letters from energy suppliers informing them of potential restrictions on the supply and consumption of electricity in the summer in the event that a higher power supply level is introduced:

“Due to the Regulation issued on November 8, 2021, regarding the detailed rules and procedure for introducing restrictions on the sale of solid fuels and the supply and consumption of electricity or heat, and based on the attached 2023/2024 energy restriction plan, we inform you that in the event of a declared reduction in energy consumption in accordance with power supply levels, we must proceed to shut down individual installations and devices in order to reduce the power consumed in accordance with the power supply points.”

Energy supply restrictions may mainly affect industrial and logistics facilities

For some facilities, the announcements of potential power restrictions are drastic, even by several hundred percent, e.g., from 3.5 MW of ordered power to 0.6 MW of safe power, or from 0.509 MW to 0.069 MW. Such a large reduction makes it practically impossible for a company to function. Energy supply restrictions may mainly affect industrial plants, logistics centers, and shopping malls. Should they come into effect, entrepreneurs will have to limit the power ordered for current use, in some cases significantly.

– The power restriction plans sent by the electricity supplier are determined every year. In the case of a large scale of potential restriction, a logistics or industrial company using electrically powered machinery should secure an alternative power source to avoid stopping operations and incurring company losses. As SPIE, we service over 220 buildings in the country, and I know that although this does not apply to everyone, there are facilities that have received restrictive power reduction plans of even several hundred percent – says Agnieszka Janowska, Project Manager at SPIE Building Solutions.

Exceeding power limits carries the risk of high penalties

Most logistics and production companies have power restriction plans and a defined so-called safe power level. Such documents state what is to be shut down first to maintain operational continuity. If necessary, devices that ensure work comfort are usually turned off first – air conditioning, ventilation units in offices, then lighting in warehouses is limited. In the final phase, all devices that tenants have on their premises as specified in the plan prepared by the FM companies servicing them are turned off. In some facilities, drastic restrictions on the use of installations in the building may appear as early as at the 14th level, in others only at the 19th – this depends on the plans sent by the electricity distributor. At the highest power supply levels, the list of devices to be immobilized can count a dozen or so items. Then it is necessary to switch to a power generator, if one is available at the facility.

– Entrepreneurs precisely define the ordered power because they pay for it. Of course, there is usually some buffer. However, it is likely not at the level of reducing electricity consumption by more than half. In such a situation, the company stops operating, cannot produce and fulfill signed contracts or deliveries to customers, which may result in multi-million penalties resulting from commercial contracts. On the other hand, failure to comply with the restriction carries the risk of very high statutory penalties from the electricity distributor – says Agnieszka Janowska from SPIE Building Solutions.

Financial penalties are provided for in the Energy Law regulations and can amount to up to 15% of the company’s revenue for the previous fiscal year. The penalty is imposed on the entity ordering the electricity. Most often, this is the owner of the facility where there are many consumers (tenants). To be able to properly plan the shutdown of installations in a facility in the event of electricity consumption restrictions, power analyzers can be used for each consumer.

– Such a device tracks the active energy consumption, prepares a forecast based on a given billing period, informs about the possibility of exceeding the contractual power, and visualizes instantaneous power consumption at the main connection with a “show, forecast, warn” function. It also records any excesses – explains Agnieszka Janowska.

Power generators can help

The possible need to limit power consumption and the risk of penalties are causing an increase in interest in power generators. Such devices can provide additional power and allow for maintaining the planned work mode for a certain period. A suggestion regarding securing an additional power source also appears in letters from energy suppliers.

Many companies reserve such devices and pay for each month of availability. However, demand is growing, so there may be a shortage of generators at a critical moment. The SPIE expert points out that in addition to guaranteeing the availability of the device, one must prepare for its connection to the existing network.

– Before ordering them, an energy balance must be developed, and it must be planned what such a device is to power – e.g., lighting or production. Data on the building and energy consumption are needed. Every building is different; it happens that one building has many transformers that cannot be connected to a single generator. In the case of wanting to purchase a generator, a connection must be made, and the best location near the facility must be planned. Making a connection costs several dozen thousand PLN, the cost of a generator depending on power and model is, for example, from 80 to 150 thousand PLN for a 100 kW generator. There are also formal issues – reporting the technical conditions of the connection with the power generating device to the energy distributor, updating the operational cooperation instructions, and in the case of the need to build foundations, building permits – explains Agnieszka Janowska from SPIE Building Solutions.

The reason is no longer war, but the climate

In the autumn of last year, 2022, there were also concerns in the industry about power restrictions. At that time, they were related to the war and the geopolitical situation, as well as the potential lack of raw materials for energy production in power plants. Now these risks have decreased, but climate change remains a significant factor. Power grids are not being modernized quickly enough. Additionally, photovoltaics are operating, which on hot days causes voltage spikes, which can lead to grid overloads.

A power restriction was nearly implemented in May 2021, when an important electrical substation failed.