Modernization of 68 carriages for the Przemyśl – Szczecin route

Modernization of 68 carriages for the Przemyśl – Szczecin route

The modernization of the first of 68 PKP Intercity carriages is nearing completion. Units of the modernized rolling stock will be delivered to the carrier in February 2013. These will be carriages refurbished at the PESA factory in Bydgoszcz. By mid-July of this year, the entire renewed fleet will be on the tracks.

At the end of July 2012, PKP Intercity signed contracts with three entities for the modernization of 68 carriages. The total value of the contracts amounted to nearly 180 million PLN, of which over 60 million came from European Union funds.
The execution of the order for PKP Intercity was handled by: H. Cegielski – Fabryka Pojazdów Szynowych Sp. z o.o. from Poznań, NEWAG S.A. from Nowy Sącz, and a consortium of Pojazdy Szynowe PESA Bydgoszcz S.A. with the company Zakłady Naprawcze Taboru Kolejowego „Mińsk Mazowiecki” S.A. The subject of the contract was the modernization of 68 passenger carriages intended for servicing the rail connection on the route Przemyśl – Rzeszów – Kraków – Katowice – Opole – Wrocław – Poznań – Szczecin, using TLK (Twoje Linie Kolejowe) category trains. One of the key elements of the modernization work is adapting the carriages to a speed of 160 km/h, which, along with the modernization works being carried out by the infrastructure manager on the line, will allow for a reduction in travel time for TLK trains operating on the Przemyśl – Szczecin route.

– The first carriages will soon leave the PESA plants. These will be 2nd class open-space carriages with space for bicycles. We recently visited the Bydgoszcz plants and saw the progress of the work. The carriages will reach us in batches, successively over the coming months. According to the schedule of the entire project, we should also soon receive the first carriages from NEWAG and FPS. Passengers traveling on the Przemyśl – Szczecin route will certainly feel a big difference in travel comfort this year – says Janusz Malinowski, President of PKP Intercity.

– A total of 38 carriages of three types will be modernized at our plant – 1st and 2nd class open-space carriages and dining cars. We are currently modernizing all types of carriages. The work is being carried out at various stages of advancement. Upon completion, PKP Intercity customers will have at their disposal a very modern product, equipped with electronic information boards, automatic entrance doors (sliding-plug), as well as power sockets and air conditioning – says Michał Żurowski, press spokesperson for PESA Bydgoszcz SA.

As part of the order, PKP Intercity is modernizing both 1st and 2nd class carriages. Some of them are being converted into open-space carriages and adapted to the needs of disabled persons. Ten carriages will be equipped with racks for transporting bicycles, and another 10 will be adapted for catering services. In the case of facilities for disabled persons moving in wheelchairs, appropriate toilet cabins will be installed, and entrance doors to carriages and compartments as well as corridors will be widened. The carriages will also be equipped with boarding platforms or lifting devices.

– Already in 2014, the number of new and modernized carriages will be higher than the number of old ones, and in 2015 these proportions will be almost one to two in favor of new trains. This means a reduction in the average age of the carriages and, consequently, an increase in travel comfort. Next year, Pendolino trainsets will also enter Polish tracks. This means that we will be able to move the currently operating rolling stock on the Tri-City – Warsaw – Katowice / Kraków route to other lines. This will be a big and positive change for the passenger – adds Janusz Malinowski.

For the first time, the carrier included a point in the order specification requiring the carriages to contain devices to boost mobile phone signals. Previously, these were installed based on an agreement with one of the mobile operators. Currently, out of nearly 1,700 carriages in operation, 568 have this type of equipment. All modernized carriages will also be equipped with air conditioning and closed-circuit toilets.

– The duration of the modernization depends on the scope of work, the necessity of performing tests and homologation, and the delivery of components, but on average it takes about 70 calendar days. The process itself consists of several main stages: dismantling of equipment, sandblasting, modernization of the car body shell, metalwork and welding, painting of the carriage body, fitting out of the carriage, and testing and homologation – lists Michał Żurowski.

The European Union is co-financing the carrier’s project under the Cohesion Fund from the Infrastructure and Environment Operational Program for 2007-2013. The total cost of the project – the modernization of 68 carriages – is 179,196,363 PLN, of which PKP Intercity will receive 60,352,675.81 PLN from EU funds.