On June 5, 2024, the cornerstone laying ceremony for the construction of the third terminal, T3, took place at Baltic Hub. The expansion of the largest container terminal on the Baltic Sea with a third deep-water quay, along with storage yards, not only strengthens its position on the Baltic but is another important step toward creating one of the largest container terminal complexes in Europe.
The ceremony was attended by members of the Baltic Hub management and supervisory boards, shareholder representatives, key stakeholders, customers, and contractors. Invited guests also included representatives of local and state authorities, including Arkadiusz Marchewka – Secretary of State at the Ministry of Infrastructure, Agnieszka Pomaska – Member of the Sejm of the Republic of Poland, Beata Rutkiewicz – Pomeranian Voivode, Aleksandra Dulkiewicz – Mayor of Gdańsk, and Dorota Pyć – President of the Port of Gdańsk Authority. The foundation act signed by them was placed in a special tube – a time capsule – which was then embedded under the investment.
– Thanks to the T3 investment, Baltic Hub will become one of the largest container terminal complexes in Europe, increasing handling capacity to 4.5 million TEU per year. This is not only a significant increase in operational potential and new development opportunities for our customers, but also benefits for the entire Polish economy and the markets of Central and Eastern Europe – said Charles Baker, CEO of Baltic Hub.
Construction of the third deep-water quay began in October 2022, and it is being carried out by a consortium of Budimex and DEME. A 36-hectare artificial island has already been created, which has increased Poland’s land area. The entire scope of dredging works has been completed, and subsequent stages of construction are now underway on the newly created island. The new 717-meter-long and 17.5-meter-deep quay, along with storage yards, will be equipped with state-of-the-art equipment – 7 STS quay cranes and 20 semi-automated RMG yard cranes, the first parts of which will be delivered as early as September 2024.
The new T3 terminal will be semi-automated, meaning operators will be able to remotely control equipment from ergonomically designed stations, ensuring a safe, efficient, and modern working environment all year round.
Baltic Hub’s handling capacity will increase by 1.5 million TEU to reach a total of 4.5 million TEU per year, which will directly translate into increased competitiveness for the Polish port sector. This, in turn, will positively influence the economic development of both the region and the entire country.
The investment is a response to the growing logistical needs of the region and global trends in maritime trade. The T3 project introduces new technological solutions that will increase productivity and efficiency while improving the safety and comfort of terminal employees. From the planning stage, the project was implemented with respect for the natural environment, with full protection of marine life and habitats in the region. Baltic Hub is committed to eco-friendly solutions, such as environmentally friendly quay equipment and special concrete that reduces CO2 emissions.
Full completion of work on the T3 terminal, including the commissioning of equipment, is planned for the end of 2025.
Source: Baltic Hub