Development opportunities and the role of the LNG terminal in Świnoujście on the Baltic, Northern and Eastern European gas market

Development opportunities and the role of the LNG terminal in Świnoujście on the Baltic, Northern and Eastern European gas market

Introduction
The LNG terminal in Świnoujście is the largest port investment of the last decades. Moreover, it is an investment that introduces a new cargo and its associated technology to the national port sector. Although the main premise behind the investment was geopolitical and strategic (ensuring the diversification of energy raw material sources for Poland), a significant challenge lies in determining the market utilization potential of the terminal in Świnoujście.

This concerns both the role that the terminal will play in this region of Europe, from both a technical and commercial point of view. Undoubtedly, the main area of the facility’s use can be identified as the supply of network gas to the domestic market (import), however, recently, more and more alternative employment opportunities for the terminal are emerging.

Project – LNG Terminal Świnoujście
In August 2008, the Polish Government adopted a resolution in which the construction of the LNG terminal was recognized as a strategic investment for our country’s interest. The premise for this decision was the plan to diversify sources and routes of natural gas supply and to guarantee Poland’s energy security. After initial location analyses, Świnoujście was chosen as the optimal place for the project implementation. Work on the technical design of the terminal was completed in 2009, and a year later, a contract was signed with the project contractor. The completion of the terminal construction is planned for June 30, 2014. The LNG terminal in Świnoujście will allow for the receipt of 5 billion cubic meters of natural gas annually.

At the same time, there will be a possibility to increase the operational capacity to 7.5 billion cubic meters without the need to expand the area on which it is located.
The basic planned functional elements of the terminal are:

  • A jetty equipped with a loading station and safety installations (port basin depth of 14.5 meters),
  • Two LNG tanks with a capacity of 160,000 cubic meters each,
  • LNG regasification station.

The port infrastructure will enable the handling of LNG tankers with a capacity of 90,000 to 200,000 cubic meters and a draft of up to 12.5 meters.
It can therefore be assumed for further analytical purposes that the level of market supply related to transshipment, storage, and regasification services amounts to 5 billion cubic meters per year. It is also worth emphasizing that the LNG terminal in Świnoujście is the first large gas terminal built on the Baltic Sea, which is particularly important in relation to its subsequent strategic position on the Baltic gas market. (…)

The article contains 42,150 characters.

Source: Logistyka Magazine 5/2012