In transport contracts, we deal with two main deadlines: loading and unloading. These deadlines are often referred to as “FIX”, which in the industry means an absolute time limit for performing these activities. The word “absolute” suggests that failure to meet the deadline should not happen at all, and if it does, it entails consequences. How do the provisions of the CMR Convention interpret this issue?
Contractual penalty and the CMR Convention
The primary tool used to secure one’s interest in the event of non-performance or improper performance of a contractual obligation is contractual penalties.
– This is an institution defined in the provisions of the Civil Code, specifically in Article 483 § 1 of the Civil Code. According to it, the parties may stipulate in the contract that compensation for damage resulting from non-performance or improper performance of a non-monetary obligation will be made through the payment of a specified sum – explains Mateusz Pernak, a lawyer at TC Kancelaria Prawna – In the context of transport law and the CMR Convention, we should also point out that the parties may extend the debtor’s liability by invoking Article 473 § 1 of the Civil Code in connection with Article 353(1) of the Civil Code, pointing to the principle of freedom of contract and contractual liability for non-performance or improper performance of an obligation due to circumstances specified in the contract.
The CMR Convention contains one provision that is of great importance in this context. This is Article 41 of the CMR Convention, which states directly that any clause that would directly or indirectly infringe upon the provisions of the CMR Convention is null and void.
What is delivery delay?
The issue of delay itself is defined by the CMR Convention in Article 19. It states that a delay in delivery occurs when the goods have not been delivered within the agreed time limit. If no time limit has been agreed, a delay occurs when the actual duration of the transport exceeds the time in which a carrier should complete the transport by exercising all due diligence.
The regulations found in the CMR Convention refer explicitly to the situation of delay in delivery, not in loading. In such a situation, the relevant provisions of national law will apply. In practice, however, a delay in loading very often also affects the delivery deadline and causes it to be exceeded.
– In most cases, we are dealing with a delay in loading, which will exclude the application of the CMR Convention. However, there are situations in which the causal link between loading and unloading becomes significant enough to treat the situation as a delay in delivery – says Mateusz Pernak.
Contractual penalty for a “FIX” deadline vs. CMR Convention provisions
If we are dealing with an agreed “FIX” deadline in a transport order, in the vast majority of cases we will also find a contractual penalty stipulated in connection with its failure to be met. Due to the aforementioned mandatory nature of the CMR Convention provisions, resulting from Article 41 of the Convention, stipulating such contractual penalties is at least debatable.
The issue of carrier liability for delay in delivery is regulated quite specifically by the CMR Convention. The carrier is liable for damages resulting from a delay in delivery – both in the case of the goods themselves and for indirect damages, for example, the remuneration of a team hired to unload the goods, contractual penalties from contractors, etc.
The CMR Convention also stipulates additional conditions that must be kept in mind in the event of a delay in delivery. As Article 23(5) of the CMR Convention states – in the event of a delay in delivery, if the entitled person proves that they have suffered damage as a result, the carrier is obliged to pay compensation that cannot exceed the amount of the carriage charges. Therefore, it is necessary both for damage to occur and to demonstrate a causal link between the damage itself and the delay in delivery. The Convention also stipulates a maximum amount of compensation equal to the amount of the carriage charges.
Furthermore, in accordance with Article 30(3) of the CMR Convention, a delay in delivery can only form the basis for compensation if a reservation has been made in writing within 21 days from the date the goods were placed at the disposal of the consignee. This is another condition that must be met to effectively claim compensation for a delay in delivery.
– Since the CMR Convention so specifically defines the rules for claiming compensation for delay in delivery – and we know that according to Article 41 of the CMR Convention, any clause in a contract that violates the provisions of the CMR Convention is null and void – it must be assumed that stipulating a contractual penalty for delay in delivery will also be considered null and void in the event of a dispute – explains the expert from TC Kancelaria Prawna – The carrier is liable for a delay in delivery, but only to the extent of the damages that actually occurred for this reason and with the limitation of the compensation amount to the amount of the freight – he adds.
Every contractual penalty will indicate a specific amount determined in advance before the execution of the order. As such, it will not constitute the equivalent of the damage that actually occurred in connection with the delay in delivery and thus will not be consistent with the provisions of the CMR Convention.
A “FIX” deadline will not necessarily affect the right to compensation
Due to the specific nature of the transport industry and the problems resulting from failure to meet delivery deadlines, the CMR Convention defines a specific procedure for claiming compensation for damages resulting from this, while simultaneously closing other avenues for dealing with this topic. A deadline defined as “FIX” should be treated with a greater degree of caution and as a priority; however, from the point of view of the CMR Convention, it will not be relevant for claiming potential compensation.
Source: TC Kancelaria Prawna