The architectural consortium, acting as the master architect, has submitted the construction design for the new airport, railway station, and public transport interchange to the CPK company. The review of the construction design has begun and is expected to be completed by the end of this year. The opening of the first phase of the airport is scheduled for the end of 2032.
– By placing the CPK company under the supervision of the Ministry of Infrastructure, we had a clear task from the beginning that aligned with the government’s overall goal: to update and make the construction of the CPK, a key infrastructure project for Poland, realistic. Today, we have another concrete step toward the creation of the central airport. The port’s construction design is ready, design work is in the final stages, and we are clearly accelerating – says Dariusz Klimczak, Minister of Infrastructure.
– This is another milestone on the path to our goal, which is the construction and launch of the new airport. This investment is an impulse for the further economic development of Poland, while simultaneously strengthening the market position of the national carrier, PLL LOT – adds Maciej Lasek, Government Plenipotentiary for CPK.
The designed area of the passenger terminal is approximately 450,000 square meters. Passenger handling will take place on three levels:
- Level +2: check-in, security control, Schengen arrivals and departures, part of Non-Schengen arrivals,
- Level +1: Non-Schengen arrivals and departures, transfer centers, document control,
- Level 0: Schengen and Non-Schengen bus gates, baggage claim hall, arrivals hall.
The main building will be connected to piers, through which passengers will reach the aircraft directly. In the first phase of implementation, the airport will be able to handle up to approximately 11,000 passengers per hour. On the opening day, there will be nearly 140 check-in counters inside, with spatial provision for the installation of another check-in island, increasing the number of counters to 170.
Preparations for construction
– In accordance with our announcements, we are consistently taking further steps in preparation for the construction of the new airport. We have received the construction documentation from the designer, which includes, among other things, approximately 6,250 design drawings and over 50 reports. At this moment, a meticulous verification of the documentation is underway – says Dr. Filip Czernicki, CEO of CPK.
The CPK master architect consortium includes design firms selected in the tender, Foster + Partners and Buro Happold, as well as over 30 other companies from various industries, including NACO, Kuryłowicz & Associates, and Cundall. In total, nearly 500 designers were involved in the work of the airport and station master architect.
– The CPK investment is an absolutely unique opportunity to design a completely new airport from scratch. Our goal was to create infrastructure that is accessible, intuitive, and clear for passengers, ensuring comfort, short transfers, and a positive travel experience. Our design focuses on passengers and their needs – emphasizes Grant Brooker, Head of Studio at Foster + Partners.
In July 2023, the CPK company received the architectural concept of the airport from this contractor, thereby moving from the third to the fourth stage of design, which is the development of the construction design. Compared to the third stage, in agreement with the investor, design optimizations were introduced that will allow for a reduction in the budget required for its implementation.
The design assumes the availability of 27 dedicated contact stands for narrow-body aircraft and 23 contact stands for wide-body aircraft (including 18 flexible MARS-type stands, which allow for the interchangeable positioning of two narrow-body aircraft in place of one wide-body aircraft) in the first phase.
In total, it will be possible to handle between 50 and 68 aircraft at contact stands equipped with passenger boarding bridges, depending on the fleet type. This will translate into a significant increase in passenger service comfort and capacity.
For comparison: at Chopin Airport, it is only possible to position eight wide-body aircraft at contact stands simultaneously, and in total, it is possible to handle between 22 and 27 aircraft at all stands equipped with passenger boarding bridges.
The CPK design assumes the integration of several types of transport – air, rail, and bus. The investor anticipates that up to half of the passengers will travel to the airport by train.
According to the updated schedule, the new airport is to be launched at the end of 2032 – simultaneously with the planned section of the High-Speed Rail between Warsaw and Łódź.
Source: CENTRALNY PORT KOMUNIKACYJNY Sp. z o.o.