Energy produced by the Baltic Power offshore wind farm has started flowing into the national power grid today. This is a historic moment for the Polish energy sector and one of the final phases in the completion of Poland’s first offshore wind farm in the Baltic Sea. 54 out of 76 turbines have been installed at sea, the first of which are already generating electricity, with construction scheduled to be completed this autumn.
ORLEN is implementing the largest investment program in the history of the Polish energy sector. We will spend a total of up to PLN 380 billion on it. Once again, we are demonstrating the real effects of our actions. Offshore work began at the start of 2025, and today the first electricity has reached the grid. This is the energy of tomorrow. Efficiently executed ambitious investments that increase energy security and will allow for offering the lowest possible prices. Baltic Power is an investment that will operate for decades – it will not only provide energy and strengthen security but will also support the construction of a new sector of the Polish economy. In parallel, we are developing a domestic supply chain and competencies that will remain in Poland long after the construction of this farm is finished. This is a value that is not measured solely in megawatts, but also as a lasting impulse for the country’s development – says Ireneusz Fąfara, CEO of ORLEN.
The achieved milestone, known as “First Power,” marks the start of energy production by the first turbine and the beginning of the gradual commissioning of the farm. In the coming weeks, subsequent turbines will undergo startup and testing. Importantly, the energy they generate will already be flowing into the national power grid. Baltic Power is starting to power Polish homes. At the same time, the entire infrastructure is being verified – from the turbines and offshore substations to the onshore substation and control systems. As work progresses, the farm’s capacity will gradually increase until it reaches the target of 1.2 GW. This is the first operation of this kind carried out in Poland.
The installation campaign is more than 80 percent complete. 54 turbines have already been installed at sea, all internal and export cables with a total length of 350 km have been laid, and the assembly of both offshore substations has been completed. All onshore infrastructure is also ready, including the substation in the Choczewo municipality. Simultaneously, dozens of specialized vessels are operating in the investment area, carrying out assembly, testing, and acceptance of subsequent farm components.
The Baltic Power service base in Łeba has been operational since last year; it currently supports construction and, after the investment is completed, will be responsible for the operation and maintenance of the farm for approximately 30 years. The Offshore Coordination Center, which manages the movement of vessels working in the investment area, also operates there. More than 100 ships and over 5,300 crew members and contractors have already been involved in the project’s implementation.
Ultimately, 76 turbines with a capacity of 15 MW each will operate at the farm, providing a total capacity of approximately 1.2 GW. Baltic Power will generate about 4 TWh of electricity annually, which will cover approximately 3 percent of the current national electricity demand. This is an amount corresponding to the needs of over 1.5 million households. The 130 sq km farm, located about 23 km from the shore near Choczewo and Łeba, uses some of the largest and most advanced turbines in the world, which have been equipped with nacelles manufactured in Poland. Energy generated by the Baltic Power farm will reduce CO₂ emissions by up to 2.8 million tons per year compared to energy production from conventional sources.
In parallel with startup work, the farm’s infrastructure will undergo further inspections and performance tests, obtain the required occupancy permits, and complete the certification process conducted by an independent auditor. These will be the first administrative proceedings of this type in Poland. Once construction is finalized, the final stage will be obtaining a license for electricity generation issued by the Energy Regulatory Office.