At the beginning of March, two components for ORLEN’s petrochemical investment arrived at the Port of Gdańsk. The gigantic columns completed their journey in Płock after 300 km of river transport along the Vistula. The Polish team of one of the world’s largest logistics operators, DSV – Global Transport and Logistics, was responsible for the comprehensive planning, execution, engineering supervision, and safety of the transport.
Two cargoes, manufactured in Shanghai, China, were delivered to the Port of Gdańsk; they are key components of ORLEN’s petrochemical investment – a concentration column and a C4 butadiene fraction column. The larger one measures 89.5 meters in length and weighs approximately 555 tons, making it one of the largest objects ever transported in Poland. The “smaller” column measures 68.5 meters and weighs approximately 288 tons.
As a logistics operator, we are responsible for the comprehensive management of the project. We were entrusted with the full organization of the cargo transport from the moment of pickup at the port in China, through sea transport and unloading at the Port of Gdańsk, to river transport including unloading in Płock and delivery to the final destination. Every element of the logistics plan was meticulously prepared, but even the most experienced team must account for unpredictable variables. – says Grzegorz Samoć, Director of the DSV Projects and Industry Solutions department in Poland.
For example, the delivery to Gdańsk took place during winter conditions. To enable the transshipment of the columns from the ship to the river barges, we had to use icebreakers to crush the ice cover, which in some places was up to 40 cm thick, so that the barges could enter the port area. – adds Grzegorz Samoć.
Two sets of connected barges carrying the cargo passed through the dam in Włocławek and reached the river port in Płock. The columns covered a total of over 300 kilometers. It should be remembered that Poland’s longest river is also the last major unregulated waterway in Europe. This makes navigability much more dependent on the influence of external factors.
We work with the best inland waterway captains to ensure the fastest possible delivery. Water levels that are too high could lead to collisions with bridges. Conversely, levels that are too low could cause the barge to run aground. That is why we carefully planned all subsequent steps, as the safety of the cargo is our priority. We are pleased that we reached Płock without any issues. – says Grzegorz Samoć, DSV – Global Transport and Logistics.
After the barges reach the river port in Płock, the next stage will be their unloading using hydraulic jacks. The columns will be transferred onto specialized multi-axle SPMT platforms and, following the preparation of roads for oversized transport in Płock, they will set off by land to their final destination, the site of the ORLEN petrochemical investment.
Source: DSV – Global Transport and Logistics