Port of Gdynia doubles the capacity of its fuel terminal

Natalia Kuna

The Port of Gdynia Authority S.A. has signed an agreement today with Budimex S.A. for the implementation of the “Expansion of the Liquid Fuel Handling Station (SPPP)” project. This marks the official start of one of the most important infrastructure investments in Polish seaports. It will strengthen the country’s energy security by enabling the handling of tankers with nearly three times the deadweight capacity than before, doubling the terminal’s annual throughput, and creating, together with the nearby PERN Fuel Base, a coherent and resilient critical infrastructure system.

Budimex S.A. has been selected as the contractor for the expansion of the Liquid Fuel Handling Station following a tender procedure conducted by the Port of Gdynia. The contract was awarded based on the concept and Functional-Utility Program developed by the AQUAPROJEKT studio.

We are implementing one of the key investments in fuel infrastructure in Poland. The scope of work is technologically advanced, and carrying out the work entirely from the water requires perfect coordination and precise planning. Budimex has experience in hydrotechnical works, and we know how important the safety and reliability of port infrastructure are. We are pleased to be able to co-create a new stage in the development of the Port of Gdynia.
– says Cezary Łysenko, Member of the Management Board of Budimex.

The investment is being carried out under a “design and build” formula, which means that Budimex is responsible for both preparing the full design documentation, including obtaining the building permit, and executing the construction works until the occupancy permit is obtained. The environmental decision has already been secured by the Port of Gdynia Authority.

We are pleased that our partner in the implementation of the SPPP will be Budimex – an experienced Polish company with whom we cooperate with full confidence. For us, this is not only a guarantee of reliable execution but also a real contribution of port investments to the development of the national economy and job creation.
– emphasizes Piotr Gorzeński, President of the Management Board of the Port of Gdynia Authority S.A.

The value of the investment is 174 million PLN gross. The documentation, along with the building permit, will be completed within 450 days, and the completion of the works is planned for the third quarter of 2028, in accordance with the schedule.

The Port of Gdynia is entering another stage of development. Parallel work is already underway on a new intermodal terminal, which will strengthen Poland’s role in European transport corridors, and today we are launching an investment crucial for the country’s energy security. Together, they form a coherent direction of change – a port that is modern, resilient, and ready for the challenges of the coming decades.
– says Piotr Gorzeński.

Three times larger ships, twice the cargo handling

The project involves the construction of a new handling pier, additional mooring and fender dolphins, new fire monitors, and a new pump station building, while integrating the existing infrastructure. Crucially, construction work will take place without shutting down the current handling station, maintaining its normal operation, which will be a challenge for the contractor. Dredging works are also planned (the technical depth of the station will be increased to 17 m), as well as strengthening the hydrotechnical infrastructure and adapting the layout to handle large LR2-class tankers: vessels approximately 300 meters long with a deadweight capacity of up to 170,000 DWT. After the modernization is completed, the annual throughput of the station will increase from 3.2 million tons to 6 million tons, which means more than a twofold increase in handling capacity.

A joint, efficient system through cooperation with PERN

The task carried out by the Port of Gdynia is complementary to the investment by PERN, which includes the expansion of the Fuel Base in Dębogórze. Both companies have signed an appropriate agreement in this regard, thanks to which the modernization of the SPPP and the development of PERN’s infrastructure create a single, coordinated system ensuring higher efficiency and resilience of the national fuel supply chain.

The largest fuel base in Poland in Dębogórze and the SPPP in the Port of Gdynia act like communicating vessels. The port investment is part of a joint system that, following the expansion completed this year – including new tanks with a capacity of 150,000 m³ and the modernization of the rail loading rack – has significantly increased its storage and distribution capabilities. This directly translates into strengthening the entire logistics system responsible for supplying the country with liquid fuels.

Ongoing investments at the Port of Gdynia

In parallel, the Port of Gdynia is conducting a number of significant infrastructure projects that strengthen its throughput, energy efficiency, and readiness for further development.

The most important activities include:

  • Intermodal terminal (under construction)
  • The new terminal, financed by the CEF instrument, includes approx. 2.7 km of new tracks, 30,000 m² of maneuvering areas, and infrastructure increasing the share of rail in cargo handling. Completion: 2nd half of 2026.
  • OPS (Onshore Power Supply) infrastructure
  • The port is developing a system for powering ships from the shore — an OPS point with a capacity of 3.5 MW is already operational, and further locations and new energy infrastructure (main power substations, networks, transformer stations) are in preparation.
  • RES and energy modernization

Renewable energy infrastructure is being expanded: photovoltaic installations on warehouses and port buildings, electrification of the technical fleet, replacement of heat sources with heat pumps, and preparations for the implementation of energy storage facilities.

Source: Port of Gdynia Authority S.A.