Panattoni, the market leader in industrial real estate in Europe, has achieved a BREEAM Excellent rating for its developed facilities for the second time. The recently completed BTS facility for e-commerce in Świebodzin, covering approximately 200,000 sqm, has successfully passed environmental certification. The investment achieved an Outstanding level score in as many as three categories.
The developer, among other things, conducted a detailed 60-year LCC analysis, installed 3,873 photovoltaic panels, implemented an intelligent Building Management System (BMS), and achieved water savings of nearly 55%. The facility has 4 levels, which will house 30 million products handled by 3,000 transport robots.
Panattoni has completed the BREEAM International New Construction certification process at the Excellent level for the BTS facility in Świebodzin, which is entirely dedicated to e-commerce. The building, with an area of nearly 200,000 sqm, is the developer’s second project in Poland to receive such a high rating – the first was the Panattoni Park Sosnowiec I distribution center. The investment in Świebodzin was rated at over 85% in three categories, which is the Outstanding level. The facility scored 89% for “Management”, 86% in the “Waste” category, and as much as 92% for “Energy”. Furthermore, water systems and solutions in the “Health and Wellbeing” category also recorded very high scores.
The entire project was preceded by a detailed Life Cycle Cost (LCC) analysis for a 60-year period, and during construction, the developer monitored electricity and water consumption as well as the impact of transport, tracking CO2 emissions. Panattoni also achieved a 96% waste recovery rate and developed a functional building adaptation strategy. In the project itself, the developer implemented numerous energy-saving solutions. The client will benefit from, among other things, photovoltaics, a Building Management System (BMS), an intelligent lighting system, and energy-efficient elevators. Furthermore, the technology used in the facility will allow for water savings of 55%, thanks to the use of devices that prevent uncontrolled leaks. In the project, the developer also ensured increased access to daylight, and office spaces were tested for thermal comfort and proper acoustics. Additionally, Panattoni provided easier access for employees of varying physical abilities and ages.
Together with the facility’s user, the developer also focused on sustainable transport, providing infrastructure for charging electric cars, promoting carsharing, and preparing 50 spaces for buses. Furthermore, both companies ensured the optimization of road traffic in the area by providing special, extended slip roads to the investment, which will help avoid congestion on the exit road to Krosno.
– The project in Świebodzin is another Panattoni investment for an e-commerce giant that combines a huge area with sustainable construction. Last year, we obtained BREEAM certification at the Very Good level for a facility in Gliwice, which occupied 210,000 sqm, and now we are moving up a level. Continuous development in the field of sustainable construction is the result of the hard work of many people, from the Panattoni team, through general contractors, to the assessors who guide us through the entire certification process. Mutual understanding allows us to deliver green and perfectly optimized facilities – says Emilia Dębowska, Sustainability Manager, Panattoni.
The newly commissioned four-story facility in Świebodzin occupies nearly 200,000 sqm, of which approximately 13,000 sqm has been allocated to the office and social zone. The facility’s volume amounted to over 1.1 million cubic meters, which will ultimately allow it to house up to 30 million products. The Świebodzin investment is the third facility of the global e-commerce leader in Poland equipped with technology using robotics. As many as 3,000 robots will work on its premises, which will significantly improve the picking and storage process. The developer ensured the preparation of a perfectly smooth floor, required for this level of automation. The facility in Świebodzin was the winner of the Prime Property Prize 2021 in the category: “Investment of the Year – Logistics and Warehouse Space Market”.
The BTS Świebodzin facility is located just about an hour from the German border, which will allow for efficient service to both our western neighbor’s market and all of Western Europe. Thanks to the S3 expressway running nearby, one can efficiently reach both the southern border and the Szczecin-Świnoujście port. The facility is also located about 20 minutes from the A2 motorway, which connects the most important centers in Central and Eastern Europe: Berlin, Łódź, and Warsaw, and also allows reaching the Poznań airport in about 60 minutes. Even closer is the airport in Zielona Góra, which is about a 30-minute drive from the facility in Świebodzin.
Source: Panattoni