Dachser Air & Sea Logistics has organized the transport of an oversized, 138-ton machine for car production. The route from Brazil to Mexico was covered in three stages.
At the end of April, Dachser transported components of a car production machine from Jundiaí, Brazil, to Silao, Mexico, with a total weight of 138 tons. The compressor – the largest part of one of the machines – weighed 125 tons. The project was extremely difficult. The machine was located in a pit about 5.5 meters deep. A company collaborating with Dachser, specializing in crane equipment, undertook the task of lifting the component out of the pit. Subsequently, the machine parts were dismantled into 14 pieces of various sizes and transported from Brazil to Mexico in three stages.
– We are constantly supporting our customers in solving complex logistics problems – says Guido Gries, Managing Director of Dachser Americas. – Heavy loads always pose a special challenge. In this case, besides expertise, the ability to think innovatively is also truly needed.
The transport of parts to the port of Santos in Brazil took place on a multi-axle platform trailer along pre-agreed routes. Due to COVID-19 restrictions, there was no police escort, and the cargo could only move through the partially mountainous terrain between 11:00 PM and 6:00 AM. Covering the nearly 160 km from Jundiaí to the port in Santos took a week.
– The project required the involvement of many people: from permitting authorities, through intermediaries and local authorities, to the logistics operator and our road transport partners. Therefore, to ensure smooth execution, it is crucial that everyone is kept up to date and fully engaged – claims Guido Gries.
Further transport to Mexico took place by ship. Together with the shipping company CMA-CGM, the Dachser Brazil team identified the type of vessel required for the transport and storage of the oversized equipment. A container ship was chosen as the fastest and most efficient option. The cargo was stored on the ship on flat rack containers and a specially constructed platform. To avoid potential collisions with terminal cranes during the loading of the heavy shipment, the Dachser team arranged for a floating crane, which allowed the crew to load on the opposite side of the ship, thus bypassing the gantry cranes.
After 30 days at sea, the cargo reached the Atlantic port of Veracruz in Mexico. The goods were transferred directly from the ship to a modular truck. Customs clearance was completed the following day.
The cargo was transported by land from the port to the production plant with additional precautions in place due to the coronavirus pandemic. Once the routes on national roads were pre-approved, the delivery schedule had to contend with temporary road closures, pre-defined time slots, and a lack of local police escort. The 700 km journey from the port of Veracruz to the client’s plant in Silao in central Mexico was covered in 3 days. Upon the cargo’s arrival at the production plant, it was unloaded from the truck by three cranes.
– Successfully completing a project of this magnitude is a great achievement – especially in the middle of a global pandemic – says Edgardo Hamon, Managing Director of Dachser Mexico. – It shows how well different national organizations in the Dachser family work together to achieve something seemingly unattainable.
Source: Dachser