The General Directorate for National Roads and Motorways has signed three contracts for the implementation of sections of the Via Carpatia road. By the end of 2020, 267.4 km of the new route will be under construction.
The idea of creating the Via Carpatia route was born in 2006. The Government Program for the Construction of National Roads for 2014-2023 (with a perspective until 2025) identifies the construction of the route as a key investment priority. The S19 expressway in the Podkarpackie Voivodeship will eventually be approximately 169 km long. Parallel work on the implementation of the S19 is also being carried out in the Lublin Voivodeship.
On June 18, 2018, contracts were signed for the implementation of three sections of the S19 expressway from the Lasy Janowskie junction (Lublin Voivodeship) to the Nisko Południe junction.
– Via Carpatia is a lifeline for Eastern Poland. That is why it is gratifying that we are signing further contracts for its implementation. Three contracts for the nearly 25-kilometer section of the S19 Lasy Janowskie – Nisko Południe are another step bringing us closer to the creation of this important artery. The new road will improve travel on the north-south axis and open the entire region to new development opportunities – said the Minister of Infrastructure, Andrzej Adamczyk.
The Lasy Janowskie – Zdziary section (approximately 9.3 km long) will be implemented by a consortium of Strabag Sp. z o.o. and Strabag Infrastruktura Południe Sp. z o.o. for PLN 236.3 million. The Zdziary – Rudnik nad Sanem section (approximately 9 km long) will be designed and built by Mosty Łódź SA for PLN 286.9 million, while the Rudnik nad Sanem – Nisko Południe section (approx. 6 km long) will be implemented by a consortium of Strabag Sp. z o.o. and Strabag Infrastruktura Południe Sp. z o.o. for PLN 196.3 million.
The contracts are of the “design and build” type. The contractors will first proceed to develop the documentation necessary to submit an application for a road investment permit. After obtaining the ZRID permit, field work will begin. All sections will be implemented within 34 months, excluding winter periods, and will be covered by a 10-year warranty. The S19 Lasy Janowskie – Nisko Południe will be built as a dual-carriageway expressway with two lanes. Drivers will be able to use the new S19 route between Rzeszów and Lublin in 2021.
Source: GDDKiA