Construction work is underway on the S7 Lubień – Rabka Zdrój expressway. The long-awaited tunnel under the Luboń Mały mountain has been broken through. The sections excavated simultaneously from both sides were connected using micro-blasts.
A twin-bore tunnel is being built on the Zakopianka route, with a length of 2060 m, as part of the S7 Naprawa – Skomielna Biała section. The investment is financed by EU funds. The right tunnel bore was broken through in October 2019. Finishing works are currently being carried out there.
– Poles have been waiting for the Zakopianka for many years. Finally, these expectations are becoming a reality. Breaking through the second tunnel bore is another important stage on the way to the goal of completing this investment – said Minister of Infrastructure Andrzej Adamczyk.
Tunnel excavation began in March 2017 in Naprawa, from the right northern portal. Work is carried out in continuous operation, 24 hours a day, 7 days a week. It requires constant monitoring for technological and safety reasons. For some time, construction activities were suspended due to a landslide at the left portal in Skomielna Biała – the investment required securing and redesigning. In June 2019, the stage of installing piles, which form the structure of the ventilation building, was completed. Subsequently, tunnel excavation began using the under-ceiling method under the ventilation building, which is located directly at the exit of the left tunnel.
Tunnel excavation was entrusted to the Astaldi company. The contractor uses the A.DE.CO.-RS controlled deformation method (analysis of controlled deformations in rocks and soils). This method was developed in Italy in the 1980s. It allows for the consideration of the interaction between the ground and the lining as a function of their respective stiffness, but also the time of deterioration of the ground properties, especially rock blocks.
– Thanks to the tunnel, drivers will be able to travel the route, which they have described as a “road of suffering” until now, in a safe and comfortable way. Speaking about the construction of the S7 on the Lubień – Rabka section, it is impossible not to mention the European Funds, which cover more than half of the road construction costs. The route will have a European dimension not only because it is being built with the support of EU funds, but also because it will connect Poland with its southern neighbors. It is of strategic importance for the ports in Gdańsk and Gdynia, and it will bring Slovakia much “closer” to the sea – said Deputy Minister of Funds and Regional Policy Grzegorz Puda.
Source: Ministry of Infrastructure