A challenging transport – Fracht FWO sends project cargo to Ukraine

A challenging transport - Fracht FWO sends project cargo to Ukraine

The logistics operator for the industry, Fracht FWO Polska, specializes in oversized and project cargo transport. Often, the delivery locations are hard-to-reach industrial facilities. Fracht FWO recently completed one such project for a company investing in the development of wind energy. It involved the transport of transformers weighing over 300 tons in total, along with equipment, to power substations under construction in Ukraine. The condition of the road infrastructure, specific formalities, and variable weather were of key importance for this project.

The cargo consisted of three transformers manufactured in a factory in central Poland, along with equipment and transformer oil. The heaviest of the units weighed 86 tons, and the other two weighed 56 tons each. The delivery locations were three substations situated in the southern part of Ukraine, about 20 km from the Crimean Peninsula. A total of 3 special vehicles and 11 trucks with curtain-sided trailers were used to transport the entire cargo. Each of the units was delivered to a different location.

Difficult access
The preparation for the transformer transport had to be meticulously planned. Fracht FWO Polska forwarders, together with their Ukrainian partner, conducted site visits to the substations where the equipment was to be delivered and checked all possible transport routes A challenging transport - Fracht FWO sends project cargo to Ukraine for the vehicles. Due to the poor condition of roads in the southern regions of Ukraine, two different options had to be designated – one for vehicles carrying heavy transformers and another for trucks with much lighter equipment. Some of the routes consisted of dirt and field roads, which hindered and slowed down the passage of vehicles with heavy equipment. In one case, due to the lack of access roads, it was even necessary to change the originally scheduled delivery date. Special attention also had to be paid to the passage of the vehicle with the heaviest transformer. Here, a major water obstacle in the form of the Dnieper River had to be taken into account. It turned out that vehicles with such heavy cargo could only cross a few bridges.

Specific procedures and formalities
Another issue was the formalities related to organizing oversized transport from Poland to Ukraine, within two customs areas (outside the EU). Ukrainian procedures differ from those introduced by the Customs Union of other former USSR countries, such as Belarus, Russia, or Kazakhstan, and require different preparation.

– The duration of the transport was also affected by border crossing procedures and the necessary coordination for the simultaneous delivery of the complete unit for customs and import clearance – both the transformer and all accessories and transformer oil. Only in such a case does the Ukrainian customs office treat the delivery as a single unit and apply preferential rates –A challenging transport - Fracht FWO sends project cargo to Ukraine adds Roman Mazurkiewicz from Fracht FWO Polska, responsible for the implementation of this project.

The transport of the heaviest transformer along the entire route through Ukraine, in addition to standard escort, had to be additionally secured and convoyed by the Ukrainian police.

Heat and off-road in the mud
When preparing the delivery of the transformers, Fracht FWO Polska forwarders also had to take into account seasonal restrictions and bans on road travel introduced in Ukraine during the summer due to high temperatures. But as it turned out during the transport, it was not only the heat that slowed down the journey. Due to heavy rainfall, driving conditions on dirt roads deteriorated.

– Heavy rains turned the already difficult dirt road into real muddy off-road tracks over a stretch of several dozen kilometers. Covering a section of about 10 km took us one day. We also had to use the help of an additional heavy tractor, because it proved impossible for the vehicle loaded with a 56-ton transformer to cover this section on its own – says Roman Mazurkiewicz.

The transport of each load, from the moment of pickup from the factory in Poland to delivery in Ukraine, took about 8-10 days. The preparation of the transport itself took over 2 months.

– Over the last few months, this was another delivery of transformers to Ukraine organized by our team. Thanks to this, we have significantly expanded our knowledge regarding the specifics of organizing and executing oversized transports in this region – concludes Roman Mazurkiewicz.

Project cargo requires knowledge and experience
– Our clients are companies from the industrial and energy sectors, for whom we carry out complex project cargo transports, including air, sea, and road freight. It often happens that cargo must be delivered to hard-to-reach places, such as power substations in southern Ukraine or a power plant in Colombia, which could only be reached through a tunnel carved in rock. Thanks to the experience and knowledge of the team and a proven network of business partners, we are ready to carry out even the most demanding orders – assures Jarosław Jankowski, business development director, Fracht FWO Polska.