This publication presents a logistics approach to the production process carried out in the longwall faces of hard coal mines in Poland. To conduct the analysis, the commonly used technology of unidirectional shearer cutting was adopted. Once access to the longwall is gained and it is put into operation, one can speak of a value stream emerging in the logistics sense.
The activities involved in the production process carried out in a longwall face include the following: shearer sumping, roof support advancement, drive advancement, conveyor advancement, shearer cutting, roof support advancement, return end advancement, roof support advancement, conveyor advancement, shearer cleaning, conveyor advancement.
Production process carried out in longwall faces of hard coal mines
Hard coal deposits currently exploited in Poland occur in the form of seams, i.e., layers lying over a large area and bounded at the bottom and top by two more or less parallel planes. To extract the coal deposit, it must be accessed, i.e., access workings must be made. Then, the field designated for exploitation is cut by roadways (headgate and tailgate), along which the exploitation is conducted.
In the Polish hard coal mining industry, the vast majority of longwall faces are operated with caving, where the cutting machine is a shearer. Most commonly, unidirectional cutting technology is used. The production cycle then includes two passes of the shearer along the longwall (one cutting pass and one cleaning pass for the shearer path) and consists of the following activities: shearer sumping, roof support advancement, drive advancement, conveyor advancement, shearer cutting, roof support advancement, return end advancement, roof support advancement, conveyor advancement, shearer cleaning, conveyor advancement.
Coal exploitation is an extremely difficult task due to the high unpredictability of the conditions under which it is conducted. Geological surveys of the deposit allow for the estimation of production parameters, but these approximations cannot always be the basis for precise calculations at the production organization stage. The occurrence of heterogeneity in the geological structure of the deposit, natural hazards, or machine failure are just some of the factors that can cause the stochastic nature of the production process carried out in mines. The course of the production process carried out in a hard coal longwall face depends on a number of factors. They can be divided into two groups: geological-mining conditions and technical-organizational conditions.
The article contains 19,130 characters.