It will be safer and the maximum train speed will increase. Revitalization works on the Żywiec – Węgierska Górka section, carried out by CTL Service, began a month ago and their first effects are already visible. The track surface has been replaced and the ballast has been cleaned.
The renovation of railway line no. 139 on the Żywiec – Węgierska Górka route is being carried out under a “design and build” system. Its contractor, CTL Service, a company from the CTL Logistics group, is responsible for preparing the design documentation and obtaining all necessary opinions, approvals, and permits for it, as well as executing a wide range of investment works. Ultimately, by the end of October, approximately 8 km of track will be replaced, a new catenary system will be built, and the platforms in Radziechowy Wieprz, Cięcina Dolna, and Cięcina will be adapted to the needs of disabled persons. Each of the three locations will also be equipped with, among other things, shelters, benches, information display cases, and new lighting. The works also include replacing the surface at 10 railway-road crossings and installing new safety devices at 3 of them. Furthermore, the task includes the renovation of 21 engineering structures, including 7 bridges.
In the month since the work began, CTL Service has replaced the track surface—replacing wooden sleepers with prestressed concrete sleepers—and carried out mechanical cleaning of the ballast. The renewal of the catenary system has been ongoing for 4 weeks.
– With such a wide scope of work, something very often surprises the contractors. However, we are at the forefront of the industry, and that is precisely why we successfully take on the most difficult challenges – says Stanisław Hołda, member of the board and managing director of CTL Service. – We are making every effort to ensure that the work proceeds according to the schedule. So far, it is going according to our plans.
Representatives of CTL Logistics are aware that the revitalization of railway line no. 139 and other renovations being carried out at the same time, e.g., in Węgierska Górka, may be burdensome not only for passengers of Koleje Śląskie but also for the residents of this part of the Silesian and Żywiec Beskids.
– Construction work always involves certain inconveniences. We are minimizing these difficulties as much as possible. With the local residents in mind, we are using heavy equipment to a minimal extent – says the CEO of CTL Logistics, Grzegorz Bogacki. – By the end of October, we will finish the work related to the catenary system and track works. The results of our work will serve the region’s residents for many years. I think that in a few months, everyone will appreciate it.
The revitalization of railway line no. 139 on the Żywiec – Węgierska Górka route is being carried out as part of the investment project titled “Works on railway line no. 139 on the Czechowice-Dziedzice – Bielsko Biała – Zwardoń (state border) section.” The value of the section’s revitalization is approximately PLN 43 million and is financed from the state budget.