Construction of the new Mint of Poland facility is now complete

Construction of the new Mint of Poland facility is now complete

The Pekabex Group has completed the assembly of the prefabricated structure for the new production facility of the Mint of Poland, currently under construction in Warsaw’s Białołęka district. Work is progressing according to schedule, and is even slightly ahead of it.

The facility is being erected on a 2-hectare plot on Annopol Street in Warsaw, in the Białołęka district. The Mint of Poland plans to relocate its coin production from the city center to the new 7,800-square-meter hall.
The general contractor for the new production plant is the Pekabex Group.

– On Monday, May 18, we installed the final element of the prefabricated structure. We produced, delivered to the construction site, and installed a total of 203 elements, including columns and beams made using traditional reinforcement technology (reinforced concrete) as well as roof beams and girders made as prestressed elements. The remaining work is proceeding according to plan, and in some cases, we are even slightly ahead of schedule – said Przemysław Borek, CEO of Pekabex Bet, a company within the Pekabex Group responsible for the project’s execution.

– The construction of the production hall for the Mint of Poland is one of those projects where we have utilized the unique competencies of the Pekabex Group in terms of comprehensive investment implementation, meaning we are responsible not only for the production and delivery of prefabricated elements but also for the assembly of the structure on the construction site and the execution of accompanying construction works, including those related to external infrastructure – pointed out Przemysław Borek.

The completion of all work carried out by the Pekabex Group on the construction of the new Mint facility is planned for October 2015.