Modernization of the runway at Ławica

Modernization of the runway at Ławica

Poznań-Ławica Airport has finalized the operational aspects of the runway modernization, which is necessary due to current technical parameters and the requirements of ICAO (International Civil Aviation Organization).

Construction work will last from April to October 2015. For technical reasons, a temporary 24-hour closure of the runway is necessary, planned for the turn of September and October. The runway modernization investment, planned since 2007 as part of the airport’s multi-year expansion program, aims to improve the safety of flight operations. The preparation stages included assessing the technical condition based on studies, as well as conceptual and design work. The timeline depends on the scope of construction work and technological requirements, as well as weather conditions such as temperature or precipitation. The modernization will last from April to October 2015, but the peak intensity of work is scheduled for early autumn. This means restrictions on flight operations, including the complete closure of the runway.
The work schedule includes the period from September 21 to October 11 of this year. During the months of highest passenger traffic, i.e., from mid-June to the end of August, work will be carried out outside the runway area, so the runway will be used normally during this time. During the rest of the modernization period, usage restrictions will apply at night. Passenger traffic handling during the complete runway closure depends on the carriers, who make autonomous decisions regarding the organization of their aircraft operations.
The necessity to carry out the modernization in 2015 results from the degradation of the runway’s load-bearing capacity confirmed by studies. According to calculations, the current state and continued operation will not allow for the handling of flight operations performed by the most popular Airbus A320 and Boeing 737 aircraft in the near future of 3-4 years. The effect of the modernization, in addition to solving the diagnosed technical problems, is to increase safety and comfort of use through: pavement reconstruction, construction of a new drainage system, construction of new navigation lighting (preparation for the introduction of Category II instrument landing system), and construction of an icing warning system. The modernization will also enable the handling of aircraft with increased weight, even with a higher number of take-offs and landings. This investment is co-financed by the European Regional Development Fund under the Wielkopolska Regional Operational Program (WRPO).